posted by Barbara Clarke on Jun 6, 2019, 4:07 pm

We have the calculations sf for our existing exterior...

If treatment is used, cycles may exceed the number of cycles i the Table

NC-v4 WEc3: Cooling tower water use
posted by Sue Bryant on Jun 25, 2019, 3:52 pm

The FORM in LOL next to the Table: Potable water analysis, says that if treatment is used, cycles may exceed the number of cycles in the Table. 

What does this mean? If treatment is used,...

Reclaimed water from off-site

NC-v4 WEc1: Outdoor water use reduction
posted by HoMU WELLTECH on Jul 2, 2019, 12:22 pm

Hello.

Our project is in a very dry area, with very little rain. The design team has already chosen plant species with very low water needs (over 40% reduction) but, to supply with the...

Ventilation Requirement for High Rise Residential

NC-v4 EQp1: Minimum indoor air quality performance
posted by Jay Murray on Jul 3, 2019, 10:07 am

Question: Is it necesary to hard duct ventilation air into each bedroom within the apartment? Or...is it adequate to provide all of the required ventilation for that apartment in one location (ie...

Following Strategy A but no D for regularly occupied space

NC-v4 EQc6: Interior lighting
posted by Edgar Arevalo on Jul 12, 2019, 11:12 am

I'm working on a project, where indirect overhead lighting for a regularly occupied space (garbage truck maintenance garage space) would not be feasible due to height restrictions for vehicle...

Entryway system extends into elevator

NC-v4 EQc1: Enhanced indoor air quality strategies
posted by Angela Barreto on Jul 12, 2019, 5:25 pm

Hi,

we have a project with a complying entryway system at ground level. However, the LEED reviewer has pointed out an entryway system is also required at the elevator lobby in our...

Electrical Buses as an Innovation Credit

NC-v4 INc1: Innovation
posted by on Jul 22, 2019, 12:26 pm

A Mass transit project will be using Electric buses to serve the routes. As for LTc8 Green Vehicles, the project already has preferred parking and EV charging stations covered. The LEEDv4...

Option 3, Exterior wall repair and repointing

NC-v4 MRc1: Building life-cycle impact reduction
posted by Edgar Arevalo on Jul 23, 2019, 4:26 pm

For this project, certain brick...

5 Year contracts delivered annually

NC-v4 EAc7: Green power and carbon offsets
posted by Heather Schrock on Jul 31, 2019, 12:46 pm

Hi! I am a...

MERV 11 in garage unit

NC-v4 EQp1: Minimum indoor air quality performance
posted by Johanna Koch on Aug 8, 2019, 3:25 am