Baseline Projects with Several Physically Distinct StructuresHospitality-NC-v4 EAp2: Minimum Energy Performanceposted by MICHAIL MENTZOS on Sep 18, 2023, 3:37 am
We are currently working on a project which has a total area of about 4,000m2. The project consist of several buildings, each of them is no more than... Last reply: Marcus Sheffer, Sep 22, 2023, 11:29 am |
|
Baseline for Projects with Several Physically Distinct StructuresNC-v4 MPR3: Must comply with project size requirementsposted by Mike Mentzos on Sep 15, 2023, 6:57 am
All, We are currently working on a hotel project, which consists from several buildings the sum of them is about 4,000 square meters. Each individual bulding is not greater than 2,300... |
|
Rainwater ManagementNC-v4 SSc4: Rainwater managementposted by Ribert Senzoga on Sep 5, 2023, 12:52 pm
I am evaluating the Rainwater Management of a warehouse project where the water table is very high and we don't have enough depth to make a water basin. Does LEED have any suggestion to deal with... |
|
ventilation in Walk-in CoolersWarehouses-NC-v4 EQp1: Minimum indoor air quality performanceposted by Francesco Passerini on Sep 5, 2023, 12:53 pm
Hello, is ventilation in Walk-in Cooler necessary for the prerequisite? Does the request depend on the indoor setpoint temperature? If ventilation is necessary, do you have any suggestion... Last reply: Dave Hubka, Sep 5, 2023, 1:23 pm |
|
locker romsPilot-Credits WEpc147: All-Gender Restroomsposted by Belén Palao on Apr 27, 2022, 12:45 pmPaula Melton Editorial Director BuildingGreen, Inc. LEEDuser Moderator 179 thumbs up April 28, 2022- 11:21 am Hi, Miguel! I'm hoping someone on here might have an answer for you. However, just keep in mind that posting to LEEDuser is not the same as writing to LEED Coach. This is an independent grassroots forum. The email for LEED Coach is leedcoach@usgbc.org. Log in or register to post comments Zeynep Cakir LEED AP BD+C, WELL AP, Sustainable Building Consultant ECOBUILD LEEDuser Basic Member 10 thumbs up March 13, 2023- 9:12 am Dear Miguel, Have you received any feedback from the LEED... Last reply: Vanessa Hostick, Aug 14, 2023, 12:05 pm |
|
All campus occupants will use showerheads inside our buildingNC-v4 WEp2: Indoor water use reductionposted by Paola Moschini on Aug 7, 2023, 8:30 am
Our building is on a campus (industrial facility where all workers need to make a shower at the end of the worktime) and our building provides restroom facilities with showerheads for all other... Last reply: Emily Purcell, Aug 7, 2023, 12:14 pm |
|
Option 2- Carbon dioxide monitoringNC-v4 EQc1: Enhanced indoor air quality strategiesposted by Marina Curto on Mar 8, 2019, 5:32 am
We are working on a New Construction - Warehouse project that has two separate spaces (offices + warehouses). There are no densely occupied spaces with the expected occupancy considered. Are we... Last reply: Mohammad H Abbasi, Jul 31, 2023, 5:30 pm |
|
Ventilation WarehousesNC-v4 EQp1: Minimum indoor air quality performanceposted by Helena Garcia on Jun 20, 2016, 4:12 am
We are certifing a project with two buildings, the first is an offices, the second is a warehouses to rent in Spain. Last reply: Emma Loris, Jul 26, 2023, 12:28 am |
|
Ventilation in corridorsNC-v4 EQp1: Minimum indoor air quality performanceposted by Luana Jerez on Jul 18, 2023, 9:30 am
We are working on an office building 17 meters wide, on one floor, the layout is a 3.5-meter distribution corridor, serving as a division between two rows of offices. These offices are equipped... |
|
Timber lattice roofNC-v4 SSc5: Heat Island Reductionposted by Jose Miguel Gonzalez on Jul 18, 2023, 4:12 am
Hi everyone, For the calculation of the heat island on the roof of a building, we have an open terrace where a part of it is covered by a wooden lattice... |