UL Certificate of Conformity

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Donald Green  on 

We have a product that has a Foorscore symbol on their cutsheet, however when we requesed the certificate number and dates we were sent a UL Certificate of Conformity (haven't seen this before). T

6
Default Avatar
White + GreenSpec
LEEDuser Basic Member
59 thumbs up
Fri Jul 12, 2013, 7:56 pm

Not include demolition waste?

NC-2009 MRc2:Construction Waste Management
posted by  Courtney Royal  on 

Hello, I am involved with a project whom has an existing building on the site but will take it down to building another building.

3
Sr. Sustainability Consultant
Taitem Engineering
LEEDuser Basic Member
36 thumbs up
Fri Jul 12, 2013, 7:46 pm

How to handle IEQc6.1 if there are no workstations

NC-2009 IEQc6.1:Controllability of Systems—Lighting
posted by  James Del Monaco  on 

I am currently working on a Performing Arts Center that includes only shared multi-occupant spaces (classroom and auditorium) and does not include any individual occupant areas.

2
Fri Jul 12, 2013, 3:14 pm

Stair Pressurization Fans and Booster pumps

NC-2009 EAc3:Enhanced Commissioning
posted by  Bob Crowell  on 

Are the following systems required to be tested under the LEED Commissioning Scope? 1. Stair Pressurization Fans 2. Domestic Water Booster Pumps 3. Grey water reuse system Thank you,

4
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Fri Jul 12, 2013, 2:56 pm

Credits remain pending after design final review

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Daniel Müllner  on 

Hey guys, maybe you can help me understand my design review score! Following situation: I have had a couple of credits "pending" after preliminary design review mostly because some prerequisites w

2
Default Avatar
VP of Innovation
Sustainable Investment Group
LEEDuser Basic Member
110 thumbs up
Fri Jul 12, 2013, 8:10 am

Minimum/Mandatory Requirements for, VAV TU?

NC-2009 EAp2:Minimum Energy Performance
posted by  Jorge Torres-Coto  on 

I have a Tenant Improvement that has VAV terminal units connected to an existing VAV AHU. The contractor and owner decided to save money and utilize stand alone control.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 11, 2013, 7:58 pm
4
Thu Jul 11, 2013, 4:54 pm

Chillers COP consideration equivalent

NC-2009 EAp2:Minimum Energy Performance
posted by  Mohd Imran Shaikh  on 

Hi There, We are looking into a project which an office building and is going to be LEED certified.

5
Thu Jul 11, 2013, 2:47 pm

Residential Building - How to go ahead without using a survey?

NC-2009 SSc4.1:Alternative Transportation—Public Transportation Access
posted by  Prachee Mishra  on 

I am helping a residential development in New York City see if they can get LEED certification. The project is located in downtown Manhattan with close proximity to subway lines, ferry, bus lines.

3
LEED AP BD+C, O+M, Green Globes Professional
JLL
LEEDuser Basic Member
112 thumbs up
Thu Jul 11, 2013, 1:28 pm

Proposed v Baseline Outdoor air

NC-2009 EAp2:Minimum Energy Performance
posted by  Joseph Snider  on 

I am working on a multifamily building. The proposed system is a Rooftop unit with constant vlume and 100% outdoor air.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 11, 2013, 8:22 am