Our building is mostly naturally ventilated. One of the seven floors, however, has a central air system installed that serves three densely occupied conference rooms. Which case (or cases) do we need to follow? All 3?
In addition, we do not currently have a Building Automation System. Will this be required to achieve this credit? Is a BAS required for Case 3?
Any comments or suggestions would be greatly appreciated. Thank you!
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
February 8, 2011 - 8:26 am
Melissa, from what you say it sounds like cases 2 and 3 are appropriate here.A BAS is not strictly required to earn the credit, but as discussed above, it helps. Given that the area subject to case 2 is relatively concentrated, though, perhaps it would be cost-effective to pursue the credit without a BAS.