Interior element reuse in different project

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Nadia Azzam on Aug 16, 2023, 1:33 pm

Our project is demolishing a wall partition which is going to be reused on a different project (not the one applying for LEED). In this case, can the first project claim points under LEED's...

Interior Reuse- is pipework and air duct Interior non structural elements?

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by shashank gangil on Aug 23, 2018, 4:25 am

We are doing a LEED CI V4 project. The client will use existing air duct, diffuser, grilles, provided by the landlord and AC chilled water pipe. Can this be counted towards Interior non...

Last reply: Grace Heraly, Jul 6, 2023, 1:13 pm

Calculations for demountable partitions

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Marie Miller on May 3, 2023, 4:30 pm

I'm working on a TI project and we're trying to get the Design for Flexibility point. When calculating for this credit, do we use linear feet or square feet of the product? I'm guessing we...

Design of flexibility- Can an open ceiling be counted as an accessible ceiling?

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Michael on Apr 4, 2022, 2:54 am

Hi LEED experts, my interior Office wants to have an open ceiling, where people can see and access the piping, ductwork system, and HVAC machines hanging below the ceiling...

Last reply: Sarah Buffaloe, Apr 15, 2022, 12:18 pm

Option 5- 50% recyclable content by cost

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Anna McGee on Dec 4, 2018, 5:10 pm

How does one prove that "... at least 50% of nonstructural materials, by cost, are reusable or recyclable, as defined by the Federal Trade Commission Guide for Use of Environmental Marketing...

Last reply: Aleksandra Prawda, Dec 11, 2020, 8:13 am

Required documentation- credit form versus reference guide

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Dee Spiro on Aug 6, 2020, 10:56 am

I'm posing this question under this particular credit, but it's actually applicable to a number of credits in a number of the rating systems.  For this credit, the credit form includes the reused...

Last reply: Dee Spiro, Aug 6, 2020, 11:34 am

If bare raised floor is covered with carpet- is it reused?

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Diana Nezamutinova on Aug 26, 2016, 9:34 am

1. In our fit-out project in London the...

Last reply: Mark Ragucci, Apr 27, 2020, 10:04 am

Interior reuse calculation, What is counted?

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Mark Ragucci on Apr 27, 2020, 9:40 am

Our project is on the second floor of a 3 story building. To start the space has had finishes removed for hazardous abatement before construction demo. The calculation sheet says to take into...

Option 3 flexible lighting control system required documentation

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Alara Brinton on Dec 21, 2017, 11:30 am

I'm not entirely sure what the LEED online form/template means in regards to calculations for flexible lighting control system. The form says to "provide a lighting schedule and calculations...

Last reply: Izabela Kwiecinska, Sep 26, 2019, 5:21 am

Option 3- Plug and Play

CI-v4 MRc2: Interiors life-cycle impact reduction
posted by Michael Smithing on Oct 26, 2017, 7:40 am

Does anyone have any real idea what a Plug-and-play power or lighting control system is?  Our electricians consider our bus bar power distribution system to be plug-and-play but this almost seems...

Last reply: Izabela Kwiecinska, Sep 25, 2019, 5:26 am