Tenant doesn't install water fixtures- can automatically get 1 point for Option 1- water analysis?CI-v4 IPc1: Integrative processposted by Michael on May 12, 2022, 1:15 pm
Hi, My project is interior retail, and they don't install any sanitaryware fixtures in tenant scope. In IP credit, option 1, LEED asked to assess the water fixtures according to WE pre Indoor... Last reply: emily reese moody, May 13, 2022, 6:14 pm |
|
LEED Interpretation 10471CI-v4 IPc1: Integrative processposted by Dave Hubka on Apr 15, 2021, 2:04 pm
I just learned from a LEED review report that owner's renovating their own space must "identify one or more viable locations, undertake the comparison outlined in Site Selection requirements, and... |
|
Denied by not doing " use of ongoing feedback mechanisms ". How can we appeal?CI-v4 IPc1: Integrative processposted by Jorng-ren Chern on Dec 24, 2019, 2:11 am
Our LEED ID+C V4 IP credit was denied and the following review comment was provided: Site Selection and Energy-Related Systems The form narratives indicate that occupant... Last reply: Renee Shirey, Jan 2, 2020, 9:46 am |
|
Requirements for "Ongoing Feedback Mechanism"?CI-v4 IPc1: Integrative processposted by Renee Shirey on Aug 6, 2019, 7:23 pm
The requirement of "Briefly describe the planned method for gathering feedback on occupant satisfaction. Include information on sample sizes, timing, and format." sounds an awful lot like... Last reply: Marcus Sheffer, Sep 3, 2019, 3:08 pm |
|
LEED CI v4 in a CS V2009CI-v4 IPc1: Integrative processposted by Gabriela Mena on Apr 19, 2017, 11:38 amcertification, and then cross-checked that section with the other sections of the guidelines to make sure it was consistent. You can find an example of a submission on the forum page dedicated to CS v3, SS Cr... Last reply: Summer Minchew, Nov 8, 2018, 9:41 am |
|
Simple Box energy model- required?CI-v4 IPc1: Integrative processposted by Katarzyna Toczynska on Jul 16, 2018, 10:06 am
Dear all, I have a question concerning Simple Box energy modeling. Is it really necessary to perform an energy model at this point or will a narrative from the schematic design be ok? What... Last reply: Waleed Yagoub, Sep 25, 2018, 12:51 pm |
|
OPR BODCI-v4 IPc1: Integrative processposted by werdah shahid on Sep 17, 2018, 11:10 pmMarcus Sheffer LEED Fellow 7group / Energy Opportunities LEEDuser Expert 5903 thumbs up September 18, 2018- 11:24 am Check out the commissioning forums. I think there might be samples there. Log in or register to post comments emily reese moody Sustainability Director, Certifications & Compliance Jacobs LEEDuser Expert 475 thumbs up September 18, 2018- 11:35 am Indeed, you can find example templates on the prereq page under the Documentation Toolkit. You may need to have a full subscription to be able to see the content there. https://leeduser.buildinggreen.com/credit/CI-v4/EAp1#tab-docs Log in or register... Last reply: emily reese moody, Sep 18, 2018, 11:35 am |
|
Simple Box energy model requirementsCI-v4 IPc1: Integrative processposted by Deborah Stadler on Jun 13, 2018, 11:49 am
What exactly is required to be submitted for documentation for the simple box model? We see the worksheet and narrative listed as required documentation for this credit. There is so much... Last reply: Marcus Sheffer, Aug 13, 2018, 11:03 am |
|
Not eligible if no non-potable water?CI-v4 IPc1: Integrative processposted by emily reese moody on Mar 21, 2017, 5:07 pm
It appears that a project may not be eligible for the 1 point associated with the Water Related System if their building(s) do not offer non-potable water sources. Is this correct? Regardless of... Last reply: emily reese moody, May 15, 2018, 10:01 pm |
|
partial credit?CI-v4 IPc1: Integrative processposted by Dana Piper on Apr 10, 2015, 5:44 pm
If the tenant is remodeling existing space or the move location is predetermined, is it possible to get 1 of 2 points if we start in pre-design and look at energy and plumbing systems? Last reply: Mandy Lee, Jan 8, 2018, 9:16 am |