Topic | Recent |
---|---|
Waste Stream Audit AFTER Performance Period?EBOM-v4 MRp1: Ongoing purchasing and waste policyposted by Heather Enos-Graves on Oct 17, 2022, 4:41 pm
Once the performance period closed for our project, we realized that we did not divert 75% of ongoing waste as required by the prerequisite. Can we perform the alternative waste stream audit now... Last reply: Randi B., May 25, 2023, 4:45 pm |
|
MR-prerequites and criteriasEBOM-v4 MRp1: Ongoing purchasing and waste policyposted by Alice Andersen on Oct 7, 2020, 6:31 am
I am doing a certication of an office building. In this connection I would like to know which prerequisites and criterias that includes purchasing food in the calculations? I think it is a... |
|
Combined PurchasingEBOM-v4 MRp1: Ongoing purchasing and waste policyposted by Ryan Hoffman on Aug 15, 2017, 2:40 pm
The project in question is the north building of a 2-building, 1 million sf facility. Ongoing purchases and cleaning products are purchased for both the north and south facilities as a whole and... Last reply: Trista Brown, Aug 28, 2017, 2:11 pm |
|
European standards for bio-based materialsEBOM-v4 MRp1: Ongoing purchasing and waste policyposted by Ana Villarroya on Feb 24, 2017, 6:34 am
I'm working on a building's purchasing and waste policy and I'm using LEED's template. In section iv (procedures and strategies for implementation) it states that bio-based products shall meet... Last reply: Michael Smithing, Feb 28, 2017, 12:02 pm |
|
Consumable Materials for EquipmentEBOM-v4 MRp1: Ongoing purchasing and waste policyposted by RYAN BEN SABILALA on Feb 16, 2017, 7:18 am
Just want to make sure if the consumable materials like oils, gaskets, O-rings etc. used for HVAC units and water pumps are excluded in MR credit category during Policy and plan formulation and /... Last reply: Trista Brown, Feb 24, 2017, 12:46 pm |
|
Ongoing purchasing and waste policyEBOM-v4 MRp1: Ongoing purchasing and waste policyposted by VISHESH AGARWAL on Oct 21, 2016, 2:24 am
Thanks in advance Last reply: Trista Brown, Oct 21, 2016, 6:29 pm |
|
Waste Stream AuditEBOM-v4 MRp1: Ongoing purchasing and waste policyposted by Trevor Anderson on Apr 26, 2016, 11:19 am
Under LEED v4, is the waste audit requirement the same for projects achieving initial certification and recertification, or do recertifying projects need to conduct one waste audit for each year... Last reply: Trevor Anderson, May 5, 2016, 1:32 pm |
|
Ongoing Consumables in HC ClinicEBOM-v4 MRp1: Ongoing purchasing and waste policyposted by Michelle DiPenti on Oct 27, 2014, 4:28 pm
Is there a clear answer on which ongoing consumables to include in the policy? As I go down the list of our "most purchased product categories based on total annual purchases," I'm finding some... Last reply: Susan Walter, Jan 16, 2015, 3:58 pm |
|
EBOM on Core and Shell (not LEED) buildingEBOM-v4 MRp1: Ongoing purchasing and waste policyposted by LEED Pro Consultant on Jan 13, 2015, 2:13 pm
We are in the process of certifying a Core and Shell building which does not have a previous LEED certification. There is an inquiry regarding tenant engagement and responsibilities, in order to... Last reply: Anne White, Jan 13, 2015, 3:18 pm |
|
Waste stream auditEBOM-v4 MRp1: Ongoing purchasing and waste policyposted by Michael Smithing on May 18, 2014, 3:54 pm
We have been unable to achieve the waste stream audit credit in Hungary as waste haulage is government controlled and the waste haulers are unable (or unwilling) to provide this service. Any... Last reply: Anne White, Jan 13, 2015, 2:34 pm |