Forum quick links
Concrete
NC-2009 MRc5:Regional Materialsposted by Steve Willey on
Is there anyway to calculate for cost per pound for cement, fly ash, limestone and sand
Greenhouse gas emissions factors - following guidance from ACP EApc95
NC-v4 EAc7:Green power and carbon offsetsposted by Shannon Oletic on
Hello,
MR credids
NC-v4.1 MRc4:Material Ingredientsposted by Kristi Merdler on
My project is using a pre-fabicated panel (walls and ceilings) inclusive of doors, windows and ceiling grid lights. All of these components are part of the panel design.
ONSITE RENEWABLE ENERGY FOR PREREQUISITE
NC-v4.1 EAp2:Minimum Energy Performanceposted by Jorge Lopez de Obeso on
Is it possible to meet the Prerequisite and Credit with onsite renewable energy under V4.1 ?
Non default use time for lavatory faucets
NC-v4 WEc2:Indoor water use reductionposted by Ruju Rathod on
We would like to use a non default lavatory faucet duration of 15 seconds instead of the 30 seconds.
Frit: Views versus Bird collision deterrence
Pilot-Credits SSpc55:Bird collision deterrenceposted by Kath Williams on
Following design decisions, our team discovered the frit pattern chosen to deter bird collision ultimately interfered with obtaining Views credit.
Monitoring requirement for CAV/VAV system or fan?
NC-v4 EQp1:Minimum indoor air quality performanceposted by Camilo Velez on
Good afternoon all,
Exemplary performance threshold under v4.1?
NC-v4.1 SSc4:Rainwater Managementposted by Casey Cullen-Woods on
Is anyone able to locate if there is a revised threshold for exemplary performance under v4.1 of this credit? My particular project is a non zero lot line
Rainwater Management- Exemplary Performance
NC-v4 SSc4:Rainwater managementposted by LUCY WILLIAMS on
Per page 194 of the v4 BD+C Reference Guide, the Exemplary Performance section indicates "Manage 100% of rainwater that falls within the project boundary". This is a fairly vague stateme
Tool for LCA
NC-v4.1 MRc1:Building Life-Cycle Impact Reductionposted by Martin Maribo on
Can the Danish tool, LCAbyg, for MR Credit: Building Life-Cycle Impact Reduction be used for a project in Denmark?