EQc4 - IAQ Assessment, Option 1. Flush-Out, Path 1. Before Occupancy

NC-v4 EQc4:Indoor air quality assessment
posted by  Theresa Lehman  on 

If the humidity exceeds the range (higher than 60%) for a couple of hours, can the team simply add those few hours onto the flush-out, or does the flush-out have to start completely over at the tim

1
Mon Aug 29, 2022, 9:44 pm

Green area reserved for future building development

NC-v4.1 SSc2:Protect or Restore Habitat
posted by  Michael   on 

My project has 2 phases of development. Currently, we only apply LEED for phase 1. There is a big greenery area, reserved for future building in phase 2.

1
Wed Sep 21, 2022, 6:52 pm

Interior Project Water Performance

EBOM-v4.1 WEc1:Water Performance
posted by  yingling guan  on 

For interior project, if there is only one pantry faucet within the project scope.  And occupants of this project will use other indoor water fixtures or fittings installed out of the thi

1
Wed Apr 5, 2023, 1:59 pm

How to scrutiny the local testing agency's report for LEED Low emitting materials?

Retail-CI-v4.1 EQc2:Low Emitting Materials
posted by  Sagar Siripuram  on 

Hello, I've been having this doubt for many days, Just wanted clarity on this query. 

1
Fri Sep 9, 2022, 10:29 pm
5
Default Avatar
Sustainability/LEED Executive
co-energi (Pvt) Ltd.
LEEDuser Basic Member
7 thumbs up
Fri Aug 26, 2022, 12:50 pm

Compliant EPR Programs

NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials
posted by  Amanda Tullos  on 

Has anyone had luck getting credit for a take back service program like Steelcase's (https://www.steelcase.com/services/#recycle

10
Senior Project Manager
Zinner Consultants
LEEDuser Basic Member
110 thumbs up
Thu Aug 25, 2022, 4:30 pm

building on campus with no smoking policy

CI-v4 EQp2:Environmental tobacco smoke control
posted by  Megan Valentine  on 

We are renovating a building on a campus. The campus has a no smoking policy with signage stating the policy at all entrances to the campus.

0

Campus approach: can we install water meter for the entire landscape, sanitaryware as a whole

NC-v4 WEc4:Water metering
posted by  Michael   on 

My project is a campus project, consisting of 4 individual buildings. To fulfill this credit, can I install 1 meter to monitor sanitaryware for 4 buildings together as a whole?