SSpc14 Walkable project Site

Pilot-Credits PC14:Walkable Streets
posted by  Amanda Johnson  on 

I am trying to register for this Pilot Credit (which is not listed as closed) Both LEED Online and LEED User link to the USGBC Credit Library, but in the credit Library I find no link to register.

3
Fri Apr 3, 2015, 3:28 pm

Actual Material Cost vs. Material Cost: what's the difference?

NC-2009 MRc4:Recycled Content
posted by  Marcio Alberto Casado Pereira  on 

We received a review comment regarding credits MRc4 and MRc5 of a stadium we are working on in Brazil.

20
Default Avatar
Sustainability Consultant
Dagher Engineering
LEEDuser Basic Member
51 thumbs up
Fri Apr 3, 2015, 1:30 am

District cooling system with different construction planning

NC-v4 EAp2:Minimum energy performance
posted by  Jeroen Sap  on 

I have a project at hand with a high LEED ambition. They have the opportunity to connect to a future district cooling system (high efficiency).

3
LEED AP BD+C
Deerns Nederland B.V.
LEEDuser Basic Member
2 thumbs up
Wed Apr 1, 2015, 11:32 pm

Car Dealership

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Robert Shields  on 

We are working on a project to build a Toyota Dealership in Pennsylvania and the owner is seeking LEED Certification (LEED 2009).

2
President
HJKessler Associates
LEEDuser Basic Member
41 thumbs up
Wed Apr 1, 2015, 8:32 pm
7
Wed Apr 1, 2015, 6:36 pm

Rainwater storage tank TSS removal efficiency

NC-2009 SSc6.2:Stormwater Design—Quality Control
posted by  Manuel Martin Delgado  on 

Hi. We have designed a rainwater storage tank for dirty rainwater, with a bigger capacity than required. The water, after being storaged for a while, is pumped to the local sewerage system.

2
Wed Apr 1, 2015, 12:33 pm

Naturally ventilated corridors

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Stella Stella  on 

In one of our project we have a Main corridor that is completely open with just a parapet wall and roof overhang. Now we have another small corridor that is connected to this Main corridor.

11
Wed Apr 1, 2015, 11:27 am

Non-motorized rights-of-way

Pilot-Credits PC14:Walkable Streets
posted by  Florian Schmidtchen  on 

We have a building located in a pedestrian area. The only "street frontage" faces directly to this 20 m wide area.

2
Default Avatar
Technical Director
Perkins+Will
LEEDuser Basic Member
0 thumbs up
Wed Apr 1, 2015, 2:26 am

farmers

Pilot-Credits SSpc82:Local food production
posted by  Matthew VanSweden  on 

Out of curiosity, has anyone in pursuit of this credit or in its development talked to an actual farmer [or grower]?

3
Director of Intersectional Professional Services
LEEDuser Basic Member
41 thumbs up
Tue Mar 31, 2015, 7:54 pm

Must I continue to audit if 50% is reached during PP

EBOM-2009 MRc7:Solid Waste Management—Ongoing Consumables
posted by  Vanessa Seibert  on 

Our building did divert 50% of ongoing consumables during out last LEED EBOM certification in 2010. We did perform a waste audit at that time so we acquired MRc6.

5
Principal, Architect
Verde Concepts
LEEDuser Basic Member
34 thumbs up
Tue Mar 31, 2015, 5:53 pm