Slab / Floor Insulation, is it mandotary
Homes-v4 EAp1:Minimum energy performanceposted by Omar Elrawy on
Hi,
For the prerequisite requirement to add R-19 insulation to floor / slab under energystar, is it required on every floor?
Knowing that all floors are airconditioned,
If all products in one category comply with the VOC emissions evaluation do we need to list the cost or surface area?
NC-v4 EQc2:Low emitting materialsposted by Summer Gorder on
We are having a tough time getting the costs from our subs. The subs says that the cost is bundled with other material and they can't break it up.
Can Core and Shell point thresholds apply to New Construction projects with 50% unregulated energy cost in LEED v4?
NC-v4 EAc2:Optimize energy performanceposted by Michael on
Hi LEED experts, in LEED v4.1, NC projects with more than 50% unregulated energy cost can apply CS point thresholds to count points. I would like to ask if LEED v4 also applies
Moving a building
Schools-NC-v4 MRc5:Construction and demolition waste managementposted by Kath Williams on
Instead of demolition or deconstruction, this project will move an entire building across the street to another site on the campus.
Can you turn on RTUs to help dry materials and test equipment prior to building construction completion?
NC-v4 EQc3:Construction indoor air quality management planposted by Karen Shilo on
In the case of drying materials and to help run some tests for the commissioning processes to make sure building equipment is functioning properly, can you turn on RTUs prior to buil
What suggestions are there for the case of moisture damage from rain?
NC-v4 EQc3:Construction indoor air quality management planposted by Karen Shilo on
Is it possible to utilize heating systems during new construction in order to dry out some moisture damage from rain prior to construction completion?
Question regarding Occupancy sensor
NC-v4 EAp1:Fundamental commissioning and verificationposted by Nagaraj Sankar on
How can we show and prove, here are the palces we gave an ocupancy and daylight sensor for manufacturing project? and Is there gudelines used to follow to place sensor on
Commingled Waste v4 Documentation
NC-v4 MRc5:Construction and demolition waste managementposted by Samantha Lee on
What is required to be submitted for commingled waste in LEED Version 4? Does the commingled waste have to sent to a Certified Recycling Institute?
exhaust fan/fume hood
Schools-NC-v4 EQp3:Minimum acoustic performanceposted by Kai Starn on
Hi, working on a new school k-12 project with a chemistry lab. Does the 40 dBA background noise requirement need to be met concerning the fume hood?