Whether to just upload the Tables of contents for Fundamental Cx documentation review?

NC-v4 EAp1:Fundamental commissioning and verification
posted by  zz kelvin  on 

When a document is submitted for review, is it understood that only the tables of contents  needs to be uploaded, and the detailed document content does not need to be uploaded?

5
Architect - Cx Provider - Building Performance Specialist
GLHN Architects & Engineers
LEEDuser Premium Member
25 thumbs up
Wed Sep 24, 2025, 7:25 pm

OPR & BOD & Design Document review

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Dave Hubka  on 

Fundamental Commissioning requires the CxA to review the OPR and BOD and design documents.

2
Architect - Cx Provider - Building Performance Specialist
GLHN Architects & Engineers
LEEDuser Premium Member
25 thumbs up
Wed Aug 9, 2023, 11:03 pm

Question regarding Occupancy sensor

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Nagaraj Sankar  on 

How can we show and  prove, here are the palces we gave an ocupancy and daylight sensor for manufacturing project? and Is there gudelines used to follow to place sensor on 

0

Interpretation of text relating to Envelope

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Keith Fahy  on 

Hi, see here an extract from the Reference Guide: "The envelope must be covered in the OPR and BOD, but full envelope commissioning is not required unless the project team pur

0

Contractor is not able to comply with Cx Specifications

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Timothy Ian Middleton  on 

We have a project where the contractor is not able to comply with the Cx Specifications and Testing Procedures provided by the CxA.

3
Thu Apr 7, 2022, 9:51 am

Site Visits for Commissioning Agent?

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Kasandra Martin  on 

What is the average number of site visits for the Commissioning Agent?  It appears a summer and winter for HVAC.  One prior to occupancy and then one several months after everything has b

0

Potential non-compliance with regulation

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Timothy Ian Middleton  on 

Our CxA is stuck on points of compliance with local regulations.

2
www.afogreenbuild.com
Green Building Consultant
LEEDuser Premium Member
249 thumbs up
Thu Dec 23, 2021, 4:01 am

On site visits required?

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Kasandra Martin  on 

The project I am hired to commission is a day drive.  Is it possible to only review the contractors tests or is on site necessary or required?

1
Thu Sep 30, 2021, 6:42 pm

Commissioning Authority's LEED experience

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Maria Moran   on 

At the Fundamental Commisioning and Verification Prerequisite it says that the CxA must have documented commissioning process experience on at least two building projects with a similar scope of w

8
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Wed May 5, 2021, 7:19 am