Requirement of Measurement for a new ventilation system

EBOM-v4 EQp1:Minimum indoor air quality performance
posted by  Krithikha Muthukrishnan  on 

We are working on an existing factory project. It is mechnically ventilated in most spaces and those have been measured.

1
Fri Nov 22, 2024, 11:57 am

FEES FOR BASEMENT AREA

LEED v4.1 Discussion Forum
posted by  Subrota Roy  on 

 Is it necessary to calculate the basement area when we calculate the gross floor area?For feea. If this area is not only used as parking but also used as some function as storage.

0
3
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Jul 14, 2025, 9:04 am

Bicycle credit doubts

NC-v4 LTc6:Bicycle facilities
posted by  Deva venkat  on 

Hi team, i have doubts in bicycle credit.my project location is Bangladesh government using common road for two wheeler and four wheelers. Here how i get points in bicycle credit. 

0

Regarding Embodied Carbon/LCA Optimization

NC-v4.1 MRc2:Environmental Product Declarations
posted by  Nagaraj Sankar  on 

In this credit, How can I prove that my  purchased material has compile with Embodied Carbon/LCA Action Plan or other impact reductions .

1
Sun Jan 8, 2023, 6:02 pm

Question regarding Occupancy sensor

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Nagaraj Sankar  on 

How can we show and  prove, here are the palces we gave an ocupancy and daylight sensor for manufacturing project? and Is there gudelines used to follow to place sensor on 

0
2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Mon Dec 19, 2022, 4:16 am

Carbon emission for Electrical Energy and Natural gas

NC-v4.1 EAc2:Optimize Energy Performance
posted by  SAMY Chamy  on 

Dear Concern

Our project is located in Bangladesh and we are looking for carbon emissions per unit of electricity production and 1 m3 of natural gas usage.

 

0
2
Tue Dec 29, 2020, 10:52 am

Certification Timeline for a registered Project

NC-v4 MPR3:Must comply with project size requirements
posted by  Radhesh Sarkar  on 

Project is underconstruction and 60 % completion of gross project work. Now project is registered under LEED v4 BD+C of https://www.leedonline.com/projects. 

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Fri Dec 11, 2020, 1:01 am