Entryway systemCI-v4 EQc1: Enhanced indoor air quality strategiesposted by RAMON CHRISTOPHER MEDRANO on Nov 17, 2021, 10:11 pm
I have a office space project, that will have an entryway system (walk off matt). My question is where is the accaptable way to install the walk of matt it should be 10-feet (3meters) inside the... Last reply: Andrey Kuznetsov, Jun 23, 2024, 6:02 am |
|
LEED ND Plan on Indoor Water Use ReductionND-Plan-v4 GIBp3: Indoor water use reductionposted by Michael Wahjudi on Oct 30, 2020, 4:27 am
Hi all, Under GIB Prerequisite: Indoor Water Use Reduction, as the concept plan might be limited on details on fixtures and fittings. Are we able to use letter of undertaking on maximum... Last reply: Eliot Allen, Jun 22, 2024, 5:03 pm |
|
Calculating FTEs and regularly occupied spaces: AuditoriumCalculating FTEsposted by Carlos Bueno on Jun 18, 2024, 3:23 pm
Hello everyone, I have a question: I need to calculate the FTEs and define the areas of regular occupancy for a convention center that includes office spaces and two event halls that could... Last reply: Andrey Kuznetsov, Jun 22, 2024, 6:39 am |
|
Minimum Program Requirements- Must use a reasonable site boundary: site + buildingNC-v4 MPR2: Must use reasonable LEED boundariesposted by Theresa Lehman on Jun 21, 2024, 10:59 am
This is a complex, multi-part question. An airport project is being phased and has multiple contracts. The scope includes replacing the runways and concrete around the terminals. This is one... Last reply: Deborah Lucking, Jun 21, 2024, 11:29 am |
|
Are jet bridges inside or outside the building envelope?NC-v4.1 EQc2: Low-emitting materialsposted by Theresa Lehman on Jun 17, 2024, 6:27 pm
I am working on an airport project. Are jet bridges (Division 11), considered to be inside or outside the building envelope? Last reply: Deborah Lucking, Jun 21, 2024, 11:09 am |
|
Pilot Credit INpc155Pilot-Credits INpc155: Design for Indoor Air Quality and Infection Controlposted by Roxanne Button on Jul 12, 2021, 4:13 pm
Has anyone attempted this Pilot Credit yet? Our project is a college science building which was under construction during the COVID-19 shutdown, and already incoporates most of the requirements... Last reply: Michelle Halle Stern, Jun 21, 2024, 10:53 am |
|
Can the Shower Rooms be included in the Tenant's Sale Lease Agreement?CS-v4 LTc6: Bicycle facilitiesposted by Nadia Garcia on Apr 18, 2024, 3:59 pm
Hello LEED community, I'm seeking clarification regarding the Bicycle Facilities credit requirements in LEED v4 BD+C: Core & Shell, specifically regarding the inclusion of shower... Last reply: Andrey Kuznetsov, Jun 21, 2024, 10:42 am |
|
If i demonstrate prerequisite compliance with calculator and further if my project uses recycled water then will project be awarNC-v4 WEc1: Outdoor water use reductionposted by Nandan Tavkar on Jun 19, 2024, 5:39 am
If i demonstrate prerequisite compliance with calculator and further if my project uses recycled water then will project be awarded as 100% reduction (2 points)? Please confirm Last reply: Andrey Kuznetsov, Jun 21, 2024, 10:40 am |
|
LEED PC 66 Community Contaminant PreventionPilot-Credits EApc66: Community contaminant prevention - airborne releasesposted by Amanda Brathwaite on Apr 16, 2015, 4:55 pm
There are some applications, such as LPG (liquid petroleum gas) or diesel-fueled systems in remote locations, where you need to utilize combustion devices (stationary engines, boilers, etc) that... Last reply: Michelle Halle Stern, Jun 21, 2024, 10:34 am |
|
Recycled Content Report (Post-Consumer & PreConsumer)NC-v4.1 MRc3: Sourcing of Raw Materialsposted by Mu'ath Ad on Jun 7, 2024, 2:02 pm
Hi, in my current project I am dealing with a manufacturer who provided the Recycled Content with percentage report with mention whether is post-consumer or pre-consumer for some reasons. ... Last reply: Andrey Kuznetsov, Jun 21, 2024, 10:34 am |