Hot Gas ReheatNC-v4 EAp2: Minimum Energy Performanceposted by Nicolas Martinez Ochoa on Sep 19, 2022, 6:49 pm
Hello everyone, We are working on a project with dehumidification, which has a hot gas reheat to decrease the heating load after the cooling stage. Can I claim savings because of... Last reply: Cory Duggin, Sep 19, 2022, 7:16 pm |
|
LEED ID+C: Commercial Interiorsv4- LEED v4 LEED CommissioningCI-v4 EAp1: Fundamental commissioning and verificationposted by Tamer Qsoos on Sep 19, 2022, 12:45 pm
Hi, As LEED... |
|
Whether to just upload the Tables of contents for Fundamental Cx documentation review?NC-v4 EAp1: Fundamental commissioning and verificationposted by zz kelvin on Sep 19, 2022, 12:24 pm
When a document is submitted for review, is it understood that only the tables of contents needs to be uploaded, and the detailed document content does not need to be uploaded? In addition, the... Last reply: Dave Hubka, Sep 19, 2022, 12:40 pm |
|
Precertification process deliverablesLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Julio Fernandez Amodia on Sep 16, 2022, 4:53 am
Hi there, This is Julio, I am currently carrying out a LEED CS v4 certification for a shopping mall. The client is asking for a precertification, but I am unfamiliar with the process. I... Last reply: Vanessa Montezuma Ramos, Sep 19, 2022, 11:31 am |
|
Pilot CreditPilot-Credits IPpc101: Integrative processposted by AMIR ZULKHAIRI AHMAD BANGI on Sep 19, 2022, 1:22 am
As per the requirements of the pilot credit, we are noting our participation in this forum. |
|
LEED O+M v4 Pilot Credit ParticipationPilot-Credits IPpc101: Integrative processposted by AMIR ZULKHAIRI AHMAD BANGI on Sep 19, 2022, 4:36 amPaula Melton Editorial Director BuildingGreen, Inc. LEEDuser Moderator 183 thumbs up September 19, 2022- 8:58 am Hi, Amir! I think the idea behind this requirement is that you say something about your experience with the credit to help others who may be pursuing it. I doubt "We are noting our participation in this forum" is going to count as participation. Log in or register to post comments ... Last reply: Paula Melton, Sep 19, 2022, 8:58 am |
|
Future Solar Panels on RoofCS-v4 SSc5: Heat Island Reductionposted by James Jin on Sep 16, 2022, 11:55 am
Hi all, I am working on a project with rooftop solar panels planned. A portion of the solar panels will be initially installed during building construction, and the rest will be installed... Last reply: James Jin, Sep 16, 2022, 1:08 pm |
|
Parking & Retail Potential for LEED O&MEBOM-v4.1 SSc4: Site managementposted by LEED Team on Sep 16, 2022, 9:21 am
We are looking to certify a mixed use parking and retail... |
|
Strategy 4. Filtration of Recirculated AirCS-v4.1 EQc1: Enhanced indoor air quality strategiesposted by Alto ingénierie on Sep 16, 2022, 3:20 am
Hello! Can we consider strategy 4 Filtration of Recirculated Air( from the credit Enhanced Indoor Air Quality Strategies) reached by default if we have no recirculated air? ... |
|
Definition of "movable partitions"NC-v4 EQc6: Interior lightingposted by Stacey Olson on Jan 16, 2020, 4:46 pm
This appears obvious, but looking for sanity / /confirmation. Can you please confirm "movable partitions" exclude doors? It is a correct understanding that when calculating this credit, door... Last reply: Denise Bevilaqua, Sep 15, 2022, 6:57 pm |