Hi,
I am working on a LEED Healthcare project. The hospital building is phase 1 of a number of phases within a large master plan area. The Central Utility Plant will supply energy to the entire master plan area and is located in a separate building, adjacent the hospital. The CUP is currently excluded from our LEED boundary.
Is it required that we follow the guidance in the USGBC Document: Treatment of District or Campus Thermal Energy in LEED V2 and LEED 2009 – Design & Construction (Aug 13,2010)?
If we follow this guidance, does the CUP need to be modeled? Does commissioning of the CUP have to be carried out?
Alternatively, is it possible not to follow this guidance and treat the CUP as a DES?
Many thanks in advance for your help.
Add new comment
To post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.