I am working on multiple building campus level projects which fall under same contract and same owner. After the completion of schematic design stage the entire development was tendered for design and build contract. So now under a main contractor design team is working on detail design and the construction is in progress concurrently.
1.Architects are developing detail design – build contractor is working on site wide enabling work.
2.Once architect frees their drawings, MEP consultant will developed their detail design while build contractor will start the piling work/building envelop etc.
3.Followed by interior design work and then interior finishes/MEP installation by build contractor

We planned to have split review design and then construction review for LEED certification but since there will be very thin line in separating the design and construction stages anyone out there with design and build project experience can advise whether project is still applicable for split review? And any precaution should I be taking not to unsatisfied any credits requirements?

PS: I am using AGMBC 2010 (Part 1 using master site approach)
Thank you
Regards