Forum quick links
Dedicated Central OA Unit
CI-v4 EQp1:Minimum indoor air quality performanceposted by Jalal Avades on
Our project is a Commercial Interior in two floors of an existing tower. The floors are served by 4-pipe fan coils.
Exemplary Performance
CS-v4 SSc5:Heat island reductionposted by Emmanuel Pauwels on
The Reference Guide states as requirement for Exemplary Performance: Achieve both Options 1 and 2. Locate 100% of parking under cover.
Light Reflectance values
CI-v4 EQc6:Interior lightingposted by Karen Elliott on
How do you calculate the light refectance value of a glass partition?
Assigning two ac systems to a single zone
NC-2009 EAp2:Minimum Energy Performanceposted by Madushan Samarakoon on
I am working with shopping mall project. each shop has equipped with FCU units for air conditioning while separate treated fresh air AHU (PAHU) is supplying fresh air to each shop.
ERV and multiple fan coil units
NC-2009 IEQp1:Minimum IAQ Performanceposted by Courtney Royal on
Hello, I've only completed the ventilation spreadsheet a few times and have a few questions. Thanks!
Should we always display the Best Practice number?
posted by Andrea Lemon on
Should the Best Practice names always be accompanied by their number? See the attached screenshots, all taken from the main forum page:
Forums not relating to a specific Best Practice
posted by Andrea Lemon on
What general forums do you want (in addition to the Best Practice forums)? On LEEDuser we have "Forum quick links" in the left sidebar that cover general topics:
Best Practice checklist project phases
posted by Andrea Lemon on
On LEEDuser we divide checklists into multiple project phases. Specifically:
LEED for Schools 25% core space
Schools-2009 MPR2:Must be a complete, permanent building or spaceposted by Bill Swanson on
In the Rating Selection Guide there is the general rule that 60% of a space for a specific building type means that this project must be registered for that specific LEED category.
High-powered experimental equipment
NC-v4 EAp2:Minimum energy performanceposted by DAVE LI on
We have a laboratory with high-powered experimental equipment. High-power experimental equipment consumes a very high percentage of electricity.