Enhanced CommissioningNC-v4 EAp1: Fundamental commissioning and verificationposted by saif eddine majdaoui on Jun 25, 2019, 2:26 am
We are working on a big project, we are the LEED subcontractor (consultant) of the general contractor (All trades), Last reply: Scott Bowman, Aug 11, 2019, 5:49 pm |
|
FSC woodNC-v4 MRc3: Building product disclosure and optimization - sourcing of raw materialsposted by Hoda Ibrahim on Aug 9, 2019, 3:12 am
Can I use imported... Last reply: Nadav Malin, Aug 9, 2019, 9:43 am |
|
monitoring frequency of Storm Water Prevention PlanNC-v4 SSp1: Construction Activity Pollution Preventionposted by saif eddine majdaoui on Jul 2, 2019, 11:05 am
Does the monitoring of SWPP and PCES have to be carried out every week on LEED certification projects even if in the absence of rainy / weather events (No precipitation / no rain Last reply: Nischay Gowda, Aug 7, 2019, 8:53 am |
|
LESS rating levels: Design Review-Construction ReviewLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by saif eddine majdaoui on Jul 14, 2019, 8:04 am
Hello Can we ask for fewer design credits at the construction review stage? for example: Last reply: Renee Shirey, Jul 15, 2019, 11:45 am |
|
Surrounding densityNC-v4 LTc4: Surrounding density and diverse usesposted by chaima michou on Apr 1, 2019, 3:46 pm
for option 1 is the... Last reply: Kara Strong, Apr 2, 2019, 2:38 pm |
|
PROJECTS WITHOUT AVAILABLE RECYCLING INFRASTRUCTURENC-v4 MRp1: Storage and Collection of Recyclablesposted by Giuseppina Amorusi on Aug 10, 2018, 8:30 am
Hallo I have a project in a site where there are no available recycling infrastructure. In any case I would like to provide accessible recycling area to encourage waste... Last reply: Alana Cristante, Mar 11, 2019, 10:15 am |
|
ID+C Retail: Shared Outdoor air clarificationRetail-CI-v4 EQp1: Minimum indoor air quality performanceposted by Mahesh Shankar on Mar 5, 2019, 12:39 am
Hi all, The project is a retail store in Taiwan. The... |
|
Too late for SSp1?NC-v4 SSp1: Construction Activity Pollution Preventionposted by André Harms on Jan 22, 2019, 5:00 ampractices as much as possible, and put an ESC plan in place going forward. You can see examples of this situation in the LEED 2009 forum for this prereq. I haven't heard of certification being denied.... Last reply: Tristan Roberts, Feb 6, 2019, 8:50 am |
|
Stormwater Management in a project without pre-existing infrastructureNC-v4 SSp1: Construction Activity Pollution Preventionposted by Amine Zeidane on Jan 25, 2019, 4:20 am
Hello, I'm working on a mixed-use tower construction project in Morocco. The site being near a pretty big river that crosses the city, coming from the ocean nearby, the contractor... |
|
Applying MRp2 retrospectivelyNC-v4 MRp2: Construction and demolition waste management planningposted by André Harms on Jan 22, 2019, 5:07 am
A potential LEED project in Addis Ababa, Ethiopia, had already begun demolition and some construction activities before a LEED AP was appointed. The extent of the work thus far has been land... Last reply: Tiffany Beffel, Jan 22, 2019, 3:00 pm |