Slab / Floor Insulation, is it mandotaryHomes-v4 EAp1: Minimum Energy Performanceposted by Omar Elrawy on Jan 6, 2023, 4:01 am
Hi, For the prerequisite requirement to add R-19 insulation to floor / slab under energystar, is it required on every floor? The... |
|
Voltage Drop // mandatory provisions ASHRAE 90.1- 2010- ADDENDA 10218NC-v4 EAp2: Minimum Energy Performanceposted by Sara BENLOUBA on Nov 22, 2022, 8:41 am
Hello everybody, We are working on a project under LEED V4 certification. ABOUT PREREQUISITE “MINIMUM ENERGY PERFORMANCE” , we must comply with the ASHRAE mandatory provisions and... Last reply: Tyler Thumma, Dec 16, 2022, 10:13 am |
|
Current facilities requirements and operations and maintenance planEBOM-v4.1 EAp1: Energy Efficiency Best Management Practicesposted by Jeanne Perrine on Nov 9, 2022, 11:56 pm
Hello, The project we are working on is a shopping mall aiming to be LEED V4.1 (... |
|
What threshold of reverberation time to apply for Performing arts Space / ballroom?NC-v4 EQc9: Acoustic performanceposted by Sara BENLOUBA on Oct 4, 2022, 11:49 am
Hi everybody, How do you set the reverberation time values for "Performing Arts Space"? On table 2 of the LEED V4 guide page 758, nothing is written except "Vary by application". So... Last reply: Sara BENLOUBA, Oct 7, 2022, 10:02 am |
|
Airport base ratio?NC-v4 LTc7: Reduced parking footprintposted by Bouygues Sustainability on Jan 23, 2017, 10:11 am
Hello - how do i calculate the baseline parking capacity of an airport ? - it is not included in the TABLE 1 - Base Ratios for parking spaces, by building type. Last reply: Chris Flint Chatto, May 3, 2022, 4:28 pm |
|
Plan de Contrôle d'Erosion & Sedimentation / Storm Water Prevention PlanNC-v4 SSp1: Construction Activity Pollution Preventionposted by saif eddine majdaoui on Jul 1, 2019, 10:49 am
Does the monitoring of SWPP and PCES have to be carried out every week on LEED certification projects even if in the absence of rainy / weather events (No precipitation / no rain) Last reply: Robert Payette, Feb 9, 2022, 11:45 am |
|
LEED boundaries for 2 different projectsNC-v4 SSc4: Rainwater managementposted by Mohammed Fadili on Dec 30, 2021, 9:48 am
Hello all, I am currently working on the certification of 2 separated buildings with different usages (separated HVAC and plumbing systems), both are following the v4 BD+C NC. The issue is... |
|
Indoor plumbing fixtures and fittings only?NC-v4 WEc4: Water meteringposted by Amgad Khattab on Jan 1, 2020, 8:48 am
f the only subsystem available in the project is (Indoor plumbing fixtures and fittings), Are we eligible to earn this Credit for a core and shell project? Last reply: Afogreen Build, Aug 23, 2021, 4:41 am |
|
Source for Table 1 Maximum ParametersLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by indian tantrik on Aug 16, 2021, 9:46 am
Source for Table 1 Maximum Parameters |
|
CalculatorNC-v4 EAc2: Optimize Energy Performanceposted by Flavien Darthout on Jul 16, 2021, 4:48 am
Hi, I'm a beginner with the LEED v4 and the calculator for the EAc2 credit. I'm asked about the interest of the calculator. We put the simulation results in it so what is it used... Last reply: Marcus Sheffer, Jul 26, 2021, 11:24 am |