Topic | Recent |
---|---|
BMSEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Gustavo De las Heras Izquierdo on Dec 23, 2016, 12:58 pm
Hallo, We are working on two projects located in Mexico DF. One of them doesn't have a BMS and the other has a BMS but it does not provide trend graphs. Are these projects eligible for... Last reply: Scott Bowman, Jan 12, 2017, 6:05 pm |
|
Definition of LandfillNC-2009 MRc2: Construction Waste Managementposted by Adrian Arenas on Nov 28, 2016, 7:13 pmon this forum regarding mine rehabilitation? Open http://www.leeduser.com/credit/NC-2009/MRc2?all-comments=true in your browser and then search for mine. One in particular to look... Last reply: RETIRED, Dec 27, 2016, 12:23 pm |
|
Pedestrian access- Community connectivityCS-2009 SSc2: Development Density and Community Connectivityposted by Maria Isabel Conde on Dec 22, 2016, 4:47 pm
Hello, Last reply: Allison Smith, Dec 22, 2016, 5:40 pm |
|
HVAC Appropriate Zoning and ControlCI-2009 EAc1.3: Optimize energy performance - HVACposted by Gabriela Crespo on Aug 5, 2016, 12:35 pm
Dear all, We are working on a Commercial Interiors project, where there is a... Last reply: Bazeeth Ahamed K M, Nov 29, 2016, 12:56 am |
|
Appendix G OversizingCS-2009 EAc1: Optimize Energy Performanceposted by Jorge Torres-Coto on Sep 19, 2016, 12:45 pm
I have a reviewer requesting that we oversize the PROPOSED case for a "possibly conditioned in the future" warehouse. Last reply: Marcus Sheffer, Sep 19, 2016, 1:00 pm |
|
Waste Material reused "on-site"NC-2009 MRc2: Construction Waste Managementposted by Adrian Arenas on Jul 28, 2016, 2:17 pm
Construction Waste Management- Regarding waste material reused on site, our project is currently reusing... Last reply: RETIRED, Aug 19, 2016, 5:00 pm |
|
TenantsEBOM-2009 IEQc2.3: Occupant comfort - thermal comfort monitoringposted by Gustavo De las Heras Izquierdo on Jul 1, 2016, 2:09 pm
Does anyone know if all the tenants need to be included in this credit? We are working on a 70-tenants office building and I guess it will be difficult to coordinate with all of them. Is... Last reply: Ben Stanley, Aug 19, 2016, 12:48 pm |
|
Frequency of rides per day that have to be given by the shuttleNC-2009 SSc4.1: Alternative transportation - public transportation accessposted by Jorge Lopez de Obeso on Aug 9, 2016, 2:02 pm
We are working on a project in which the nearest bus stop is just over a quarter mile so it is proposed to provide a shuttle service to take users to the bus stop. The question is what should be... Last reply: Marilyn Specht, Aug 14, 2016, 8:30 pm |
|
Urinals on residencialNC-2009 WEc3: Water Use Reductionposted by Alejandro Macias on Apr 12, 2016, 2:36 pm
I m working on a dormitory for kids. On the project we have bathrooms that only will be used by the kids (I am considering them as residencial), and other restrooms that will only be used for the... Last reply: Carlie Bullock-Jones, Aug 11, 2016, 2:10 pm |
|
Manufacturing processNC-v4 EAp2: Minimum Energy Performanceposted by ignacio furniés on Aug 5, 2016, 12:10 pm
My question is regarding the EAp2 and EAc3, our project consists of a palm oil manufacturing facility. The energy intensive manufacturing process exceeds an estimated 90% of the facility's total... Last reply: Marcus Sheffer, Aug 9, 2016, 9:56 am |