MRpc103 Integrative Analysis of Building Materials

NC-v4 INc1:Innovation
posted by  Lisa Bolle  on 

As our project team was performing the analysis of three products, we realized that another potentially useful strategy would be to compare three similar products and use the integrative analysis w

2
Tue Mar 12, 2024, 9:06 pm

Pilot credit Requirement

Pilot-Credits SSpc55:Bird collision deterrence
posted by     on 

Commenting to comply with credit requirements. Credit language is clear and the team was able to implement without trouble. The project used a highly reflective glazing to comply. 

0

High Rise Residential

NC-v4 EAc3:Advanced energy metering
posted by  Megan White  on 

We have a 24 story high rise residential apartment project that wants to pursue this credit however we are looking for guidance as this seems more geared towards commercial office projects with mul

3
Chief Sustainability Officer
Integral Group
LEEDuser Basic Member
11 thumbs up
Tue Mar 12, 2024, 3:25 pm

Future open space preservation- Campus project

NC-v4 SSc3:Open space
posted by  Andy Rhoades  on 

My question is regarding a multi-phased campus project. Are we able to count future planned open space towards the credit threshold, and if so, what documentation would this require (i.e.

2
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
470 thumbs up
Tue Mar 12, 2024, 12:50 am

Lighting Control in blood draw spaces

Healthcare-v4 EQc6:Interior lighting
posted by  Heather Belsey  on 

For the lighting credit you need to have individual controls at 90% of patient positions.  LEED defines patient positions as:

0

Partial Floor LEED Certification

CI-v4 MPR3:Must comply with project size requirements
posted by  Edgar Arevalo  on 

I have a project that is a partial floor fit-out where the client would like that partial space to be LEED certified.  The project space is approximately 52% - 60% of the total floor

0

Existing PV on previously certified project

NC-v4 EAc5:Renewable energy production
posted by  Yu Zhang  on 

I have a project that is a new building located on a previous certified LEED project with PV production.  The previous project had >90% offset by energy use and >100% offset by cost from

10
Wed Mar 6, 2024, 5:20 pm

50% surface area reuse

CI-v4.1 MRc2:Interiors Life-Cycle Impact Reduction
posted by  Mark Ragucci  on 

how is this credit calculated? can in include existing floor slab and deck? we are leaving a portion of the exiting walls that are about 20ft tall and our ceilings will be at 9'.

3
Project Architect
Jacobs
LEEDuser Premium Member
0 thumbs up
Wed Mar 6, 2024, 12:34 am

Waste performance yields a score of zero points in ARC

EBOM-v4.1 MRp3:Waste Performance
posted by  jimmy Adames  on 

Hi, Our building is a very automated distribution center for an apparel company.  Due to the nature of the business, we receive cardboard cases with product and before it ships to customers, a

1