Renewable Energy - Confirmation of Renewable Attribute Ownership
CS-v4.1 EAc5:Renewable Energyposted by Levi Jimenez on
We have a site with a substantial solar array that is owned by the building owner. The LEED Credit form requires uploaded supporting documentation as follows: "upload confirmation
Option 2 Strategy E for an Atrium area - No ceiling areas (Open to roof deck above)
NC-v4 EQc6:Interior lightingposted by John Covello on
Hello.
For Option 2, Strategy E.
On site visits required?
NC-v4 EAp1:Fundamental commissioning and verificationposted by Kasandra Martin on
The project I am hired to commission is a day drive. Is it possible to only review the contractors tests or is on site necessary or required?
Industry wide EPD vs. Product Specific EPD
NC-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Caitlin Hutton on
Hello, I am attempting to achieve option one of the MRc2 credit meaning we need a total of 20 products from 5 different manufacturers.
Interior Lighting Dimming controls in Multi-use spaces
NC-v4 EQc6:Interior lightingposted by Summer Gorder on
The interior lighting of our projects has 3 zones for dorm rooms, but has dimming with manual on/ automatic off controls. There are also daylight zones.
Reclaimed water for water filtration project from watershed
NC-v4 WEc1:Outdoor water use reductionposted by Summer Gorder on
I am working on a water filtration project pursuing LEEDv4 certification for their admin building.
Design Submittal
posted by Aaron Kennedy on
We are finishing up the design submittal to submit for review, but I cannot find where the overall plans are supposed to be submitted? Am I missing it somewhere or Is there not a place to sub
CO2 monitoring in return air ductwork in a behavioral health facility
Healthcare-v4 EQc1:Enhanced indoor air quality strategiesposted by Bethany Beers on
We are currently designing a behavioral health inpatient facility in the Seattle area. Per local codes, demand control ventilation is required and is allowed in the return air ductwork for spaces.
Acoustic Point for Higher Education
NC-v4 EQc9:Acoustic performanceposted by David Harvey on
I am an acoustical consultant.