Solar Panel Energy Savings

NC-2009 EAc2: On-Site Renewable Energy
posted by DILIP bussa on Aug 5, 2015, 10:28 am

hello Marcus,

i am currently designing a navy lodge and it is 66,420 sq ft.its a Four floor building with 12 guestrooms on each floor about 900 sq. ft each.

we have solar panels...

Last reply: Marcus Sheffer, Aug 5, 2015, 10:41 am

Building Type

NC-2009 EAc2: On-Site Renewable Energy
posted by Geraldine Assmus on Jul 2, 2015, 2:07 pm

I'm trying to certify a Retail Store under LEED ID-Retail 2009 in Buenos Aires, Argentina. There is no info in Leed User for this credit.

I came across a crossroad regarding the Building...

Last reply: Marcus Sheffer, Jul 3, 2015, 11:10 am

Power generated in Mini Hydro Power Plant

NC-2009 EAc2: On-Site Renewable Energy
posted by Keerthi Ratnayake on Jun 1, 2015, 7:44 am

Hi,

We have a mini hydro power plant project. Can we accommodate the total power generated in the plant towards this credit?

Thanks!

Last reply: Marcus Sheffer, Jun 16, 2015, 2:39 pm

Elegible On-Site Energy Systems

NC-2009 EAc2: On-Site Renewable Energy
posted by Paula Hernandez on May 27, 2015, 12:18 pm

What is exactly a "Low-impact hydroelectric power systems" and how do we demonstrate that it is low-impact.
I suppose that electricity coming from a conventional hydroelectric dam is not...

Last reply: Paula Hernandez, May 28, 2015, 4:44 pm

Clarification on Solar Hot Water system eligibility

NC-2009 EAc2: On-Site Renewable Energy
posted by Sasha Peters on Apr 20, 2015, 3:56 am

Please confirm if solar hot water system is eligible for EA credit 2 - On-Site Renewable Energy compliance considering that it is only used for water heating and not generating energy directly....

Last reply: Marcus Sheffer, Apr 20, 2015, 11:17 am

Annual Energy Cost

NC-2009 EAc2: On-Site Renewable Energy
posted by Sarah Thompson on Feb 18, 2015, 5:00 pm

I am trying to figure out which cost to put in here. Another post said it was savings, although I can't find anything under the credit intent or resources for this specific item.

Last reply: Marcus Sheffer, Feb 18, 2015, 5:30 pm

Solar PV System Degradation

NC-2009 EAc2: On-Site Renewable Energy
posted by Katherine Ann Resurreccion on Feb 10, 2015, 1:45 am

Our Solar PV system supplier provided us a calculation of how much solar energy is generated per annum. It is projected that there will be a solar degradation factor of 1% each year. The...

Last reply: Marcus Sheffer, Feb 10, 2015, 8:41 am

Pre-existing Campus PV Array- Does commissioning apply?

NC-2009 EAc2: On-Site Renewable Energy
posted by Heather DeGrella on Sep 19, 2014, 4:25 pm

If we are allocating production from a campus PV array, in which the array is already built and outside of our LEED boundary, how do...

Last reply: Heather DeGrella, Sep 19, 2014, 6:04 pm

Post occupancy installation of photovoltaics as an appeal

NC-2009 EAc2: On-Site Renewable Energy
posted by Kris Phillips on Feb 17, 2014, 2:33 pm

We have a project that may be 1 point short of the next level certification after its Construction Final Review and we have been asked to look at options to add a credit or two as an "appeal" to...

Last reply: Marcus Sheffer, Aug 28, 2014, 7:36 pm

Off-site PV array with PV Developer

NC-2009 EAc2: On-Site Renewable Energy
posted by Michael Pulaski on May 14, 2014, 4:43 pm

My university client is about to sign a letter of intent for a Net Metering Credit Purchase Agreement with a PV Developer for a 650 kW array. The land is located about a mile from the project...