Log in
Forum » NC-2009 EAp2
Topic

Better to include PV in the ASHRAE model or calc outside?

NC-2009 EAp2: Minimum Energy Performance
posted by Carol Roberts on Apr 29, 2015, 9:32 am

We are working on an ASHRAE 90.1 model in Nevada and are adding the solar information manually to the LEED online forms, post energy modeling (so our solar energy is not appearing on the software...

Last reply: Marcus Sheffer, Apr 29, 2015, 9:59 am

LEED/ASHRAE definition of a preheat coil?

NC-2009 EAp2: Minimum Energy Performance
posted by Rock Ridolfi on Apr 22, 2015, 2:39 pm

The proposed system includes an ERV serving two packaged rooftop units. In the proposed, I’d like to eliminate the heating in the rooftop unit planned for morning warm-up operation but keep the...

Last reply: Rock Ridolfi, Apr 23, 2015, 9:45 am

process load

NC-2009 EAp2: Minimum Energy Performance
posted by Florian Schmidtchen on Nov 30, 2011, 8:47 am

We have currently a LEED NC project of an office building with a data center in the basement. We received the information from the electrical engineer, that the process load of the data center is...

Last reply: Jean Marais, Apr 23, 2015, 8:58 am

Infiltration rates in LEED Energy Modeling

NC-2009 EAp2: Minimum Energy Performance
posted by Arub Vijay on Nov 29, 2011, 6:47 am

I am currently doing energy modeling for a LEED Hotel project in Oman. Should I consider the ASHRAE recommended Infiltration rates in all spaces? Is there any LEED Guidelines for Infiltration...

Last reply: MARCIO OROFINO, Apr 22, 2015, 9:39 am

Existing Central Plant serving new building

NC-2009 EAp2: Minimum Energy Performance
posted by Mital Patel on Apr 20, 2015, 5:39 pm

Hello,
We have an existing central plant that will be serving new building. How do we model this? Existing central plant will service one existing building and new building. only new...

Last reply: Marcus Sheffer, Apr 21, 2015, 3:39 pm

EA advanced Energy metering credit (LEED v4)

NC-2009 EAp2: Minimum Energy Performance
posted by Angelina Ten on Apr 16, 2015, 2:30 am

Marcus Sheffer LEED Fellow 7group / Energy Opportunities LEEDuser Expert 5903 thumbs up April 20, 2015- 11:16 am There are forums for LEED v4. Please post the question in the appropriate forum so that future LEED Users will be able to find the question and response. Log in or register to post comments ...

Last reply: Marcus Sheffer, Apr 20, 2015, 11:16 am

Baseline heating set-point when no heating system exists

NC-2009 EAp2: Minimum Energy Performance
posted by Ricardo Sá on Apr 17, 2015, 7:00 am

According to ASHRAE 90.1 (2007) Table G3.1 - 10 c, "where no heating systems exist, HVAC system shall be assumed to be electric". Considering a space that has a cooling system but not a heating...

Last reply: Marcus Sheffer, Apr 17, 2015, 9:45 am

Hi all,

NC-2009 EAp2: Minimum Energy Performance
posted by Visu Boj on Apr 14, 2015, 5:57 am

I am working on a certification for a factory having less than 5 percent conditioned area. My process load is also high upto 75 percent. Can any one suggest me how to get savings in optimize...

Last reply: Visu Boj, Apr 17, 2015, 1:03 am

ASHRAE standard

NC-2009 EAp2: Minimum Energy Performance
posted by Nelina Loiselle on Apr 15, 2015, 10:33 am

Hello,

Can someone let me know if ASHRAE 90.1 2010 is acceptable to use in relation to lighting or is 90.1 - 2007 still required to be used? I have read the FAQs above, but want to make...

Last reply: Nelina Loiselle, Apr 15, 2015, 2:46 pm

ASHRAE 90.1- LIGHTING POWER DENSITY SOFTWARE.

NC-2009 EAp2: Minimum Energy Performance
posted by Ghaleb El Mheirat on Apr 15, 2015, 7:21 am

We are currenlty in the design process of a building targetting to be LEED certified under version 3.0. As per ASHRAE 90.1:2007 requirements for...

Last reply: Marcus Sheffer, Apr 15, 2015, 11:09 am