Limits for VOC content outside US, additional questions
CS-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Ernst Schriefl on
All the limits on VOC content provided in the LEED reference guide (2009 edition) are minus water (g/L minus water or g/L less water).
Determing VOC content outside of US
CS-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Ernst Schriefl on
Yesterday we had a conversation with a US manufacturer who told us that the VOC content outside the US can also be determined according to the respective national requirements.
Healthcare-v4.1 MRc5 - PBT Source Reduction - Mercury - Credit form
Healthcare-v4.1 MRc5:PBT Source Reduction - Mercuryposted by Don Jones on
Our major renovation project will use NO mercury containing lighting or devices.
1. Is there a template for this credit?
Submitting a credit during the review process which was not submitted at first application
posted by Ernst Schriefl on
I have a general question regarding the review process:
Say, you have already submitted a certain amount of credits for review and received a preliminary review.
Confirmation of Agent's Authority
CS-2009 PIf1:Minimum Program Requirementsposted by Mary Guest on
Hello!
Barriers in implementing material transparency in LEED v4 projects
NC-v4 MRc4:Building product disclosure and optimization - material ingredientsposted by SUSAN THOMAS on
I am a master's student at State University of New York College of Environmental Science and Forestry doing my thesis in Barriers in implementing material transparency in LEED v4 projects.
New project on university campus that already has 2700 parking spots
NC-v4 LTc8:Green vehiclesposted by Alana Cristante on
Hi there,
Shading by fixed construction elements - take into account for the baseline model?
NC-v4 EAc2:Optimize energy performanceposted by Sarah Leenknegt on
Hi
Summary from Appendix G:
- self-shading is not allowed to be modeled in the baseline
- manual shading devices are not required to be modeled in the baseline
Material costs necessary?
NC-v4 MRc2:Building product disclosure and optimization - environmental product declarationsposted by Tommy Linstroth on
For EPD Option 1 or MIR Option 1, it would seem you can just submit 20+ products with EPDs and not have to provide any material cost data whatsoever in the BPDO calculator, since the cost calculati