One of my V4 LEED Online projects doesn't show the arrow icons for switching to V4.1, though my other projects do show them. Is there some master "toggle-switch" I am missing to get the icons visible? I can't find any guidance for this through the USGBC/LEED sites.
Thanks, Harry
Jesse Hunt
Sustainability CoordinatorPowers Brown Architecture
2 thumbs up
June 3, 2019 - 5:56 pm
I'm having the same issue. Did you find any solution?
Thank you,
Jesse
Harry Flamm
Senior Sustainability ConsultantStantec Architecture
20 thumbs up
June 4, 2019 - 12:31 pm
I just did, finally !
I went into the "Timeline" tab at the top of the page.
Saw that my project's timeline was set for "Precert + Combined".
I then clicked on "Split". Went back into "Credits" and the 4.1 icons appeared.
It seems the icons aren't applicable during Precertification.
Give it a try.
Karen Joslin
Sustainability LeadPAE Consulting Engineers
5 thumbs up
June 4, 2019 - 1:31 pm
They also do not appear in group project scorecards yet but I was advised to just put the same NOTE on the form as you would with the icon.