Green field but planned for development in an industrial zoneNC-v4 LTc2: Sensitive land protectionposted by Thomas Tan on Nov 12, 2020, 3:05 am
Dear All, I have a project which will be built on a lot located in a industrial zone. The lot is used to be natural land but filled up with sand now. Can we claim this land is no... Last reply: Thomas Tan, Nov 15, 2020, 11:09 pm |
|
Waterbody and Wetland DefinitionNC-v4 LTc2: Sensitive land protectionposted by Senna Sabir on Jul 26, 2020, 1:44 pm
Hi everyone - just reviewing the credit definitions again for our coastal development. Would you say the requirement of 30 meters from a... Last reply: Senna Sabir, Jul 28, 2020, 10:03 am |
|
Previously Developed- Golf courseNC-v4 LTc2: Sensitive land protectionposted by PJ Ryan on May 5, 2020, 1:37 pm
Hi, I'm working on the LEED certification of a development located on land formerly used as a golf course. Would this be considerd to be 'previously developed'? Can you... Last reply: Blake Jackson, May 6, 2020, 11:35 am |
|
Existing building major renovationNC-v4 LTc2: Sensitive land protectionposted by Victoria Rios Esteve on Jan 16, 2020, 9:59 am
Hi everyone! I have the following doubt. We are about to start the certification as NC Major Renovation of an exisiting building. It is a Zero Lot Line project. Can this type of project be... Last reply: Blake Jackson, Jan 16, 2020, 11:31 am |
|
exceptions for farmland?NC-v4 LTc2: Sensitive land protectionposted by Erica Downs on Feb 5, 2019, 11:20 am
We have an... Last reply: Erica Downs, Aug 15, 2019, 2:02 pm |
|
minor improvements within the water body body buffers: grade changes necessary to ensure public accessNC-v4 LTc2: Sensitive land protectionposted by Louise Schlatter on Aug 6, 2019, 6:14 pm
Hi. I have a question about minor improvements within the... Last reply: Blake Jackson, Aug 9, 2019, 10:15 am |
|
LT CREDIT: SENSITIVE LAND PROTECTION-Developed land within <100 ft from waterbodiesNC-v4 LTc2: Sensitive land protectionposted by Ricardo Filho on Mar 8, 2019, 4:46 am
Hello, do these 2 rules: Water bodies. Areas on or within 100 feet (30 meters) of a... Last reply: Blake Jackson, Mar 14, 2019, 2:01 pm |
|
Airports and LTc2NC-v4 LTc2: Sensitive land protectionposted by Konstantina Kalliakoudi on Oct 29, 2018, 7:30 am
Hello to all, I have an airport which will be located in a place were today there are olive groves and vineyards land. LTc2 seems not achievable. I mean olive groves and vineyards... Last reply: Tristan Roberts, Oct 29, 2018, 8:55 am |
|
Greenfield with Underground UtilitiesNC-v4 LTc2: Sensitive land protectionposted by Cathal Heneghan on Sep 7, 2018, 11:21 am
Hi all My project is a green field site apart from utility services (water and electric) which run underground through a portion of the site for neighbouring buildings. Could this... Last reply: Blake Jackson, Sep 7, 2018, 7:10 pm |
|
Does a remediated Ash basin qualify for LTc2...?!NC-v4 LTc2: Sensitive land protectionposted by Olawale Taiwo on Aug 2, 2018, 12:47 pm
My project is sited on a land mass which happens to be a remediated ash basin site on a facility which is now being transformed into a gas powered plant ( from a coal plant) and has now... Last reply: Olawale Taiwo, Aug 9, 2018, 9:42 am |