Option 2 Natural land cover conditions

NC-v4.1 SSc4:Rainwater Management
posted by  Allen Cornett  on 

With the "retain on site" verbiage is there no longer an option to retain off-site?  I have a project in a development that previous buildings have met the LEED 2009 stormwater&

4
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Thu Sep 2, 2021, 7:03 pm
2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Thu Sep 2, 2021, 6:12 pm

Concrete Recycled Content

NC-2009 MRc4:Recycled Content
posted by  MT A  on 

We have the final content $ value of cementitious materials and the m3 of concrete produced as supplied by the contractor.

6
Default Avatar
LEEDuser Expert
472 thumbs up
Thu Sep 2, 2021, 3:49 pm

Is there a benefit/penalty with regard to points earned by using this method compared to a 2010 PRM comparison?

Pilot-Credits EApc111:Alternative Performance Rating Method
posted by  Eric Dixon  on 

Has anyone found that they earned more or less points by using the 2016 PRM comparison rather than a 2010 PRM comparison?

0
3
Default Avatar
Director of Sustainability
Edifícios Saudáveis Consultores (503 910 767)
LEEDuser Basic Member
79 thumbs up
Thu Sep 2, 2021, 2:21 am

Lawn Equipment Inventory

EBOM-v4.1 SSc4:Site Management
posted by  Green Projects  on 

Does this credit require to submit an inventory of all equiptment used?

1
Mon Nov 15, 2021, 7:00 pm

November Surprise?

NC-v4.1 MRc5:Construction and Demolition Waste Management
posted by  Jonathan Weiss  on 

I am hoping I read this wrong, but the current version of the credit on USGBC.org and the Addendum posting (as of early November) seems to have changed this credit significantly - Option 1 is 1 poi

22
Director of Sustainability
IPS-Integrated Project Services
LEEDuser Premium Member
1 thumbs up
Wed Sep 1, 2021, 4:53 pm
2
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Wed Sep 1, 2021, 4:10 pm

Revised Points Thresholds APC

CS-2009 EAc1:Optimize Energy Performance
posted by  Anna Korinkova  on 

We would like to clarify the possible Alternative Compliance Paths (ACP) options for the EAc1 (our project is C&S).

4
Tue Aug 31, 2021, 2:24 pm

Is utilizing aerobic processor equipment an acceptable strategy for this credit?

Pilot-Credits SSpc129:Comprehensive Composting
posted by  Annalise Dum  on 

Our project is considering utilizing kitchen equipment that uses aerobic processing to break down food waste into liquid that is then discharged via the plumbing onsite.

0