Decreasing Baseline Capacities for Unmet Load hours

NC-2009 EAp2:Minimum Energy Performance
posted by  F S  on 

Hi All,

My question is basically about how much can you decrease the baseline capacities without going to far - that might call Red flags.

1
Thu Oct 26, 2017, 7:12 pm

Table 1.4.7B - Proposed Air-Side HVAC System Schedule - Outdoor Airflow cfm

NC-2009 EAp2:Minimum Energy Performance
posted by  Maria Spastri  on 

Hi,

I need a couple of clarificaitons regarding the Outdoor Airflow that has to be listed in Table 1.4.7.B of the proposed systems. The project is located in California.

3
Default Avatar
Sustainability Consultant
AECOM
LEEDuser Basic Member
0 thumbs up
Wed Oct 25, 2017, 7:58 pm

Modeling low flow fume hoods in a Lab

NC-2009 EAp2:Minimum Energy Performance
posted by  Joyce Kelly  on 

Owner wanted all fume hoods operating with 100cfm 24:7.

3
Architect - Cx Provider - Building Performance Specialist
GLHN Architects & Engineers
LEEDuser Premium Member
25 thumbs up
Wed Oct 18, 2017, 8:12 pm

DES or NO DES?

NC-2009 EAp2:Minimum Energy Performance
posted by  Aru Sau  on 

In this project, we have one office, two plants signed up for LEED Campus.

5
LEEDuser Basic Member
4 thumbs up
Tue Oct 17, 2017, 2:49 pm

Gas vented fireplace

NC-2009 EAp2:Minimum Energy Performance
posted by  Carlos Vazquez  on 

I have a project were there is a 24,000 Btuh gas vented fireplace. Is a wall device mostly radiant heater (70-75%) with a glass panel which does not have a fan.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Oct 10, 2017, 5:16 pm

Maintenance Garage Baseline System

NC-2009 EAp2:Minimum Energy Performance
posted by  Keith Lane  on 

I'm hoping someone can help me determine the appropriate Baseline system for a Vehicle Maintenance Facility for a LEED v2009 project. The total project area is about 34,500 s.f.

3
Default Avatar
Project Engineer
GGD Consulting Engineers
LEEDuser Basic Member
0 thumbs up
Thu Oct 5, 2017, 2:55 pm

Baseline LPD for a Vehicle Driving Test ground

NC-2009 EAp2:Minimum Energy Performance
posted by  Aru Sau  on 

There is Car Driving Test Ground located outside the building, which takes power from the substation inside the building. This ground is closely resemblance of a space like car racing (i.e.

1
Thu Oct 5, 2017, 3:11 pm