Topic | Recent |
---|---|
How to claim "NC-v4 EAc3- Advanced energy metering" credit for VillasNC-v4 EAc3: Advanced Energy Meteringposted by QUANG DOAN on Jan 4, 2024, 4:15 am
Before diving deep into the question, to gain more insight into the project, please read the following overview:
Last reply: Marcus Sheffer, Jan 5, 2024, 10:44 am |
|
Location of outside airflow measuring station inside the HVAC unitNC-v4 EQp1: Minimum indoor air quality performanceposted by Edgar Arevalo on Jan 4, 2024, 1:15 pm
We have a 100% outside air HVAC with an energy recovery wheel serving the entire the project space. Since there is no recirculating air getting reintroduced to the supply side, the MEP engineer... Last reply: Edgar Arevalo, Jan 5, 2024, 10:05 am |
|
LEED Registration for 2 buildings on same plotLEED Guidance for Campuses and Multiple Buildingsposted by Pulak Goyal on Jan 4, 2024, 4:33 am
I have two buildings going for LEED v4.1 O+M Existing Buildings certification. They are connected with a bridge on 1 level. Can I register them as 1 building for certification? Or will... Last reply: Dave Hubka, Jan 5, 2024, 9:25 am |
|
Related to fresh air CalaulationNC-v4 EQp1: Minimum indoor air quality performanceposted by Nagaraj Sankar on Nov 13, 2023, 11:57 am
Hi users, 1)One of our Production building project having fresh air supply with fresh air louver opposite to the exhaust fans how can account this in fresh air calculator. 2)And how... Last reply: Gustavo De las Heras Izquierdo, Jan 4, 2024, 9:31 pm |
|
Biophilic Design as a Guiding Principle in Sustainable DesignPilot-Credits EQpc123: Designing with Nature, Biophilic Design for the Indoor Environmentposted by Carla Roubaud on Jan 4, 2024, 3:12 pm
Securing this credit goes beyond ticking boxes; it requires thoroughly blending natural elements into the architecture. For maximum benefits, biophilic design should be seamlessly integrated from... |
|
interior lighting power allowance in w/sq. mEBOM-v4.1 EAp1: Energy Efficiency Best Management Practicesposted by Pranav Deshmukh on Nov 26, 2023, 11:37 am
How to calculate interior lighting power allowance in w/sq. m? how to calculate gross light floor area ratio in w/sq. m (GLFA)? Last reply: Rock Ridolfi, Jan 4, 2024, 2:58 pm |
|
Shower in Mixed Use Residential/RetailNC-v4 LTc6: Bicycle facilitiesposted by Michelle Rosenberger on Feb 15, 2021, 2:45 pm
I am confused about the shower requirement in a residential building that has retail space on the ground floor. The guidance about Mixed Use refers to combining Case 1 - Commercial/Institutional... Last reply: Danielle Waters, Jan 4, 2024, 2:16 pm |
|
LEED v4 Heat Island Reduction- include elevator shafts and stairwell enclosures in roof calcs?NC-v4 SSc5: Heat Island Reductionposted by Julie Baines on Mar 4, 2022, 6:24 pm
Hi all, I am working on a major renovation of an existing downtown campus building. The entire roof of the building is being redone with white TPO. However, the existing elevator and stair... Last reply: Julie Baines, Jan 4, 2024, 1:20 pm |
|
Location of outside airflow measuring station inside the HVAC unitCI-v4 EQp1: Minimum indoor air quality performanceposted by Edgar Arevalo on Jan 4, 2024, 12:31 pm
We have a 100% outside air HVAC with an energy recovery wheel serving the entire the project space. Since there is no recirculating air getting reintroduced to the supply side, the MEP engineer... |
|
Runoff calculation- typical values for infiltration lossNC-v4 SSc4: Rainwater managementposted by G.J. Teunissen on Jan 4, 2024, 10:57 am
Hi, What are the standard values for the ... |