Electric vehicle charging station used in demand response strategy

NC-v4 EAc4: Demand response
posted by Martina Salonen on Aug 24, 2018, 9:14 am

quite common for the demand response programs here, but since I found no mention of this anywhere in the LEED manual nor forum, I wanted to confirm that it is acceptable strategy and whether anybody has...

Last reply: Marcus Sheffer, Dec 4, 2023, 3:41 pm

Innovation: PBT source reduction- lead, cadmium and copper

NC-v4 INc1: Innovation
posted by David Dixon on Oct 27, 2017, 11:57 am

the credit does not allow for lead in roofing or flashing.

almost all steel is recycled and the companies report minor lead in the material due to the recycled materials - the one we are...

Last reply: Ann Busker, Dec 4, 2023, 10:23 am

Healthcare-v4.1 MRc6: PBT Source Reduction- Lead, Cadmium, and Copper

Healthcare-v4.1 INc1: Innovation
posted by Ann Busker on Feb 10, 2022, 12:38 pm

Good morning, 

I am looking for examples to send my Plumbing and Electrcial Subcontractors to explain thier process for copper pipe joints and recycling the electrical wires containing...

Last reply: Ann Busker, Dec 4, 2023, 9:50 am

How can a warehouse extension project (with no regularly occupied space) comply with EQp1?

Warehouses-NC-v4 EQp1: Minimum indoor air quality performance
posted by Blake Jackson on Dec 1, 2023, 2:33 pm

I'm working on a 455,000gsf expansion of an existing facility, which will have all new/standalone systems to support the new wing. The existing facility won't be impacted, spare for the...

Last reply: Dave Hubka, Dec 4, 2023, 9:26 am

Increased Ventilation 15% and 30%- does it count as 2 strategies?

CI-v4.1 EQc1: Enhanced indoor air quality strategies
posted by Lidia Johansen on Dec 2, 2023, 7:36 am

Hello

If we achieve increased ventilation by 30% - does it count as 2 strategies (15% and 30%)?

Thanks

Lidia

LEED certification for open spaces

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by Sergio Acevedo on Dec 1, 2023, 3:34 pm

We would like our expansion project to be LEED certified.

There will be no physical separation between the existing building and the extension (no walls).

In fact, the space will be...

Does adding "green, pool and EV's" to parking onsite, yet outside our LEED Boundary, comply with these credits' intent?

Warehouses-NC-v4 LTc8: Green vehicles
posted by Blake Jackson on Dec 1, 2023, 2:50 pm

I'm working on a 455,000gsf expansion of an existing facility, which will have all new/standalone systems to support the new wing. The existing facility won't be impacted, spare for the...

Commissioning Authority

CI-v4 EAp1: Fundamental commissioning and verification
posted by padma priya on Dec 1, 2023, 1:46 am

Commissioning Authority - Please clarify this query.

Should...

Infiltration rate @ 75 Pa (ASHRAE 2016) vs. 4 Pa / 50 Pa (Design Builder Software)

NC-v4.1 EAc2: Optimize Energy Performance
posted by Ziad Zeitoun on Nov 28, 2023, 11:18 am

Hello, 

ASHRAE 2016 specifies the...

Last reply: Marcus Sheffer, Dec 1, 2023, 9:44 am

Bicycle-credit doubts

NC-v4 LTc6: Bicycle facilities
posted by Deva venkat on Nov 14, 2023, 5:40 am

Hi team, i have doubts in bicycle credit.my project location is Bangladesh government using common road for two wheeler and four wheelers. Here how i get points in bicycle credit.