Insulation in Interior walls for Vault Spaces in Data CenterNC-v4 EAc2: Optimize Energy Performanceposted by Rajat Wadhwa on Jun 22, 2023, 4:47 pm
Hi Everyone, We are modeling A Data center and the internal walls forvault spaces have insulation in them because of high temperature in the data center vault spaces, Now I am... Last reply: Marcus Sheffer, Jun 22, 2023, 4:52 pm |
|
Justification of usign the 9.6.2 Additional Power lighting in the Baseline ModelNC-v4.1 EAp2: Minimum Energy Performanceposted by Marc Maso on Jun 19, 2023, 12:22 pmsome post in this forum where the additional power has been defined as process load. For example: https://leeduser.buildinggreen.com/forum/additional-interior-lighting-power-1 We use this assumption... Last reply: Marcus Sheffer, Jun 22, 2023, 10:56 am |
|
Minimum Outside air in DCV systemsNC-v4.1 EQp1: Minimum indoor air quality performanceposted by Marc Maso on Jun 22, 2023, 9:16 am
Dear Srs, we are using the DCV strategy in one building. The doubt are when we need to ventilated or not... A room have a schedule of 8am to 18:00
|
|
Regional Priority credit for an L&T creditCI-v4 LTc1: LEED for Neighborhood Development locationposted by Cindy Quinn on Jun 20, 2023, 5:54 pm
Our project is located in an ND Gold certified neighborhood. If we pursue the LEED for ND location credit in leiu of other L&T credits, how can we receive a Regional Priority point for... Last reply: Dave Hubka, Jun 21, 2023, 9:35 pm |
|
Can you turn on RTUs to help dry materials and test equipment prior to building construction completion?NC-v4 EQc3: Construction indoor air quality management planposted by Karen Shilo on Jan 4, 2023, 9:03 am
In the case of drying materials and to help run some tests for the commissioning processes to make sure building equipment is functioning properly, can you turn on RTUs prior to building... Last reply: Alice Wilson, Jun 20, 2023, 3:51 am |
|
Multi-family Stormwater alternative documentationNC-v4.1 SSc4: Rainwater managementposted by Summer Gorder on Jun 19, 2023, 1:34 pm
Our project is in Seattle with stringent Stormwater requirements. The Civil Engineer used software that they’re required to use to size BMPs, but it does not provide the info in the calculator... Last reply: Dave Hubka, Jun 19, 2023, 2:11 pm |
|
Zone Secondary Recirculation FractionNC-v4 EQp1: Minimum indoor air quality performanceposted by Dave Hubka on Jun 19, 2023, 9:53 am
ASHRAE 62.1, Section A1.2.2 states: Er is less than 1.0 for plenum return systems with secondary recirculation (e.g. fan-powered... |
|
Creating Baseline ΗVΑC system selection based on ΑSHRAE 90.1-2010- Does Ground Floor count as….NC-v4 EAc2: Optimize Energy Performanceposted by Konstantina Kalliakoudi on Jun 16, 2023, 4:38 am
Hello to all LEED Users, Ιn our project the Building (nonresidential – 8.000 m2) consists of following levels:
Last reply: Konstantina Kalliakoudi, Jun 16, 2023, 12:27 pm |
|
Bioretention Area CalculationNC-v4 SSc4: Rainwater managementposted by on Sep 6, 2016, 5:57 pmwill be that I went to school for a long time to learn how to do this, and it isn't something you're going to learn in a forum post. You can try to follow along with that Direct Determination Method,... Last reply: Marc-André Cloutier, Jun 15, 2023, 6:42 pm |
|
Baseline System for Data centerNC-v4 EAp2: Minimum Energy Performanceposted by Rajat Wadhwa on Jun 1, 2023, 7:07 pm
Hi All, I have read som many answers regarding the baseline system for Data centers, Some are saying use system 8 some are saying use system 3 and 4, which one is the right system? I am working... Last reply: Marcus Sheffer, Jun 15, 2023, 12:39 pm |