Mechanical LoadsNC-v4.1 EAc3: Advanced Energy Meteringposted by clinton cantrell on May 30, 2024, 1:03 pm
We are having a debate on the criteria. I understand requirement to meter any load that is 10% or more of the anual load but is metering the mechanical system as a whole capable of recieving the... Last reply: Marcus Sheffer, May 30, 2024, 5:01 pm |
|
Pilot Credit EApc106 ISO 50002 Energy AuditEBOM-v4 INc1: Innovationposted by David Alemany on May 30, 2024, 11:06 am
If this pilot credit was part of a pre-requisite or credit perhaps the advantages and disadvantages could be explained of using ISO 50002 or ASHRAE Procedures to carry out energy audits for the... |
|
Innovation: WELL FeaturesNC-v4 INc1: Innovationposted by Laura Heagler on Jul 30, 2021, 12:27 pm
This innovation credit awards a point for complying with WELL Feature 87: Beauty and Design. The WELL Building Standard requires a professional narrative describing the incorporation of design... Last reply: Deborah Lucking, May 30, 2024, 12:06 pm |
|
Density CalculationNC-v4 LTc4: Surrounding density and diverse usesposted by Ahmed Abdul Rahman on May 16, 2024, 7:27 amEmily Purcell Sustainable Design Lead CannonDesign LEEDuser Expert 369 thumbs up May 16, 2024- 10:51 am Total building floor area means the area of each floor, that is, the total square footage of space within the building. Log in or register to post comments Joseph Kong LEEDuser Premium Member May 30, 2024- 10:04 am Hi Emily Purcell I am calculating Total Buildable Land, but I have read the forum that the 400m radius is not supposed to be a circle shape. Can you share the way how you demarcate the Total Buildable Land with 400m radius. Log in or register to post comments ... Last reply: Joseph Kong, May 30, 2024, 10:04 am |
|
Entryway SystemsNC-v4 EQc1: Enhanced indoor air quality strategiesposted by Lara Ibarra on Sep 15, 2020, 3:41 pm
Hi everyone, For the entryway systems, the guide doesn't specify if it has to be installed inside and/or outside the building's entrance. Does anyone know if it can be installed 5 feet... Last reply: Andrey Kuznetsov, May 30, 2024, 3:37 am |
|
Pilot Credit: Prevention Through Design CommentPilot-Credits IPpc93: Prevention through designposted by Afogreen Build on May 30, 2024, 12:48 am
To comply with this credit, the project team should fill out the Prevention Through Design worksheet (PtD) for Life Cycle Safety and Health, which is divided into two stages: Operation &... |
|
Group Approach?LEED Rating System Selectionposted by Santiago Avila on May 27, 2024, 10:42 am
Hello everyone, I am currently working on a project consisting of two residential towers (deep retrofit). Although they appear to be connected from the outside, the only connection... Last reply: Glen Boldt, May 29, 2024, 11:51 pm |
|
Products applied offsite and non-Occupied spacesNC-v4.1 EQc2: Low-emitting materialsposted by elias eid on May 28, 2024, 4:31 am
Hi all; I would ask if the products applied offsite such as(paint for steel structural sections, Aluminum profiles, Wooden doors,...) and products applied within non-occupied spaces... Last reply: Andrey Kuznetsov, May 29, 2024, 10:25 pm |
|
Modeling a backup District energy sourceCS-2009 EAp2: Minimum Energy Performanceposted by Florian Pingaud on Dec 9, 2014, 6:41 am
Dear All, I am requesting help on the energy modeling protocol for a building both connected to a stand-alone plant and a... Last reply: Andrey Kuznetsov, May 29, 2024, 9:08 am |
|
Calculations or descriptionsNC-2009 EAc5: Measurement and Verificationposted by Barbara Aguirre Garcia on May 24, 2024, 3:25 pm
For credit, is it necessary to make calculations within the plan, regarding the baseline calculation, the reporting period? Or is it just describing the elements to do the calculations? How is it... Last reply: Marcus Sheffer, May 28, 2024, 12:38 pm |