Pilot Credits in LEED 2009 for Healthcare

NC-2009 IDc1: Innovation in Design
posted by Amy Balderrama on Feb 14, 2011, 2:42 pm

There is some confusion around earning Innovation Points in LEED for Healthcare with pilot credits. Per the LEED for Healthcare rating system it is only possible to earn only one point with...

Last reply: Tristan Roberts, Feb 14, 2011, 3:16 pm

How to calculate Process Energy for CS?

CS-2009 EAp2: Minimum Energy Performance
posted by Tatjana Ernst on Feb 9, 2011, 4:27 am

Hi everyone,

we have an Core & Shell-Office Building.
We are wondering how we have to calculate the...

Last reply: Marcus Sheffer, Feb 14, 2011, 8:30 am

Submersible & Booster Pumps: Process equipment?

NC-2009 EAp2: Minimum Energy Performance
posted by Maya Karkour on Jan 31, 2011, 4:23 am

Dear all,

Should I model non-HVAC pumps such as "sewage submersible pumps" and "domestic water booster pumps" as process equipment?

Thanks!

Last reply: David Hubka, Feb 14, 2011, 8:06 am

European Certificates accepted?

NC-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Nicole Isk on Feb 14, 2011, 6:04 am

Adhesives and...

Last reply: Reinhard Oppl, Feb 14, 2011, 7:24 am

mixed use building project (mainly residential)

NC-2009 WEp1: Water Use Reduction
posted by Tarek Dalati on Jan 29, 2011, 6:49 am

i m working on a mixed use building project (mainly residential) and i have the following question:
1- for offices for example the daily usage is the summation of males usage and females...

Last reply: Karen Blust, Feb 12, 2011, 8:22 pm

Min/Max Cooling/Heating air temperatures for ASHRAE 90.1

NC-2009 EAp2: Minimum Energy Performance
posted by Jean Marais on Jan 25, 2011, 6:46 am

Is there a minimum/maximum delivery air temperature that must be up held for ASHRAE 90.1 (we're not talking about thermal comfort, but energy simulation...the fan power specification as per Appx...

Last reply: David Hubka, Feb 12, 2011, 12:39 pm

Hi Rachael, I'm not

General forums
posted by Ellen Mitchell on Feb 11, 2011, 6:27 pm

Hi Rachael,
I'm not absolutely sure about the...

Baseline Fan Power: PFP and AHU Pressure Rises

NC-2009 EAp2: Minimum Energy Performance
posted by Rodrigo Perez on Jan 31, 2011, 4:55 pm

We’re working on a 20 stories building that is seeking LEED NC v3 certification. This building considers ASHRAE’s #8 HVAC baseline system:...

Last reply: David Hubka, Feb 11, 2011, 5:42 pm

Design Submission- Table 1.8.1

NC-2009 EAp2: Minimum Energy Performance
posted by Erika Duran on Feb 4, 2011, 3:02 pm

We're working on a Residential Project, after the design submission the certification body told us that It was not clear if the Baseline case fan power was modeled correctly.

They want us...

Last reply: David Hubka, Feb 11, 2011, 5:36 pm

Graywater System

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Joseph Greene on Feb 11, 2011, 10:23 am

We have a graywater system in our building and I'm wondering if this would be subject to Fundamental Commissioning. Any thoughts?

Last reply: Scott Bowman, Feb 11, 2011, 4:50 pm