I'm working on finalizingCI-2009 EAc1.1: Optimize energy performance - lighting powerposted by Heather Anderson on Dec 21, 2011, 4:04 pm
I'm working on finalizing documentation for a LEED project. We have completed the calculations and are only looking about 15% savings. However, all the installed ballast are dimmable and all... Last reply: Dane Sanders, Dec 21, 2011, 7:17 pm |
|
If you are registered forGeneral forumsposted by Francis Chua on Dec 21, 2011, 4:26 pm
If you are registered for LEED v2.2, then you must follow AGMBC, 2005. As you mentioned, all 4 buildings must independently meet the requirements for the EQ credits. For the 2 buildings that are... |
|
Rec CenterNC-2009 IEQc6.1: Controllability of systems - lightingposted by Meredith Hunt on Jan 26, 2011, 4:58 pm
I am working on a potential recreation center and am a little confused on how individual controls would work in a space like this. The majority of the building is a big open space with 4... Last reply: Lauren Sparandara, Dec 21, 2011, 3:35 pm |
|
Shower FTE QuestionCI-2009 SSc3.2: Alternative transportation - bicycle storage and changing roomsposted by JENNIFER COMEAU on Dec 21, 2011, 1:41 pm
Our tenant has purchased a bike rack just for their suite, and appropriate signage has been installed. When working on the credit template, I am able to input the # of secure bike racks and the... Last reply: JENNIFER COMEAU, Dec 21, 2011, 2:19 pm |
|
Multiple buildings including residentialLEED Guidance for Campuses and Multiple Buildingsposted by Emmanuel Pauwels on Oct 25, 2011, 8:02 am
We would like to use the multiple buildings approach for an international project that includes a site with a hotel and one residential single family home which belongs to the owner of the hotel... Last reply: Emmanuel Pauwels, Dec 21, 2011, 12:02 pm |
|
I have posted this in anLEED Rating System Selectionposted by Lee Dingemans on Dec 16, 2011, 12:01 pm
I have posted this in an other area of LEED User as well but maybe I will get more responces with this one. We need to register a project for one of our clients and am not sure what the best... Last reply: Lee Dingemans, Dec 21, 2011, 9:16 am |
|
Project Boundaries and New ROWGeneral forumsposted by Sam Watters on Dec 20, 2011, 2:10 pm
Hello, The project that I'm working on is going to involve construction of additional rights of way in the form of a collector street/woonerf running through the project and connecting to... Last reply: Sam Watters , Dec 20, 2011, 5:50 pm |
|
Regularly Occupied Gross Area for Lighting&ViewsNC-2009 IEQc8.1: Daylight and views - daylightposted by Habitech Distretto Tecnologico Trentino on Mar 25, 2011, 9:47 am
Hello! ... Last reply: Emily Catacchio, Dec 20, 2011, 5:26 pm |
|
Mandatory Provisions for Major Renovation ProjectsNC-2009 EAp2: Minimum Energy Performanceposted by Deborah Spira on Nov 22, 2010, 4:06 am
We have a project building that is an existing building undergoing a major renovation. The building envelope will not be altered, exept for new window glazing. The HVAC-system and electrical... Last reply: Marcus Sheffer, Dec 20, 2011, 2:18 pm |
|
Re: LEED for Existing Buildings- Tenant SpaceGeneral forumsposted by David Posada on Dec 20, 2011, 1:59 pm
Quite a few multi-tenant commercial buildings have earned LEED EB O&M, and since you are only allowed to exclude up to 10% of a building's area the tenant occupying the 25% would need to... |