Forum quick links
Improper Product Claims
NC-2009 MRc4:Recycled Contentposted by Eric Shamp on
I have sort of a minor ethical crisis: I'm reviewing the website of a not-to-be-named tile manufacturer who is claiming 40% MRc4 recycled content in their product, due to the reintroduction of scra
50% Furniture Used at Another One of Our Offices
CI-2009 MRc3.2:Materials Reuse—Furniture and Furnishingsposted by Reynaldo Castro on
We are moving about half of the existing furniture from our office to another one of our office locations to be used.
email reviewer
posted by Tristan Roberts on
Lisa, sometimes it is productive to email the reviewer to provide or request clarification at this stage. I would try that as a starting point.
Re: Cancellation of project review
posted by David Posada on
You might try the Feedback form at the top of the page in LEEDonline when you are logged in there.
Qualification of CxA
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by James Chueh on
Quick question, can the contractor of building's BAS (for both the installation and manufacturer of DDC/control components) be designated to be the CxA?
What daylight modeling programs??
CI-2009 IEQc8.1:Daylight and Views—Daylightposted by Susan M. Kaplan on
We are trying to evaluate the best way of meeting this requirement through Option 1 - Simulation according to the latest (May 2011) Addenda changes (min. 10 fc on Sept.
Hotel Passengers
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Catalina A on
Are Hotel Passengers considered transients or residents?