Log in
Forum » U.S. and Canada
Topic

Existing Conditions

NC-v4 WEp1: Outdoor water use reduction
posted by Craig Graber on Jun 16, 2015, 11:22 am

This is Josef Abboud from Atelier Ten

For outdoor areas within a renovation project scope (i.e. within the LEED boundary) but not scheduled for renovation or upgrade, do the water...

Last reply: Tristan Roberts, Apr 12, 2016, 11:19 am

choosing between CS and Hospitality

LEED Rating System Selection
posted by GBD Architects on Feb 12, 2016, 1:59 pm

Hi, we have a large project coming up that will be about 43% hotel and the rest CS. Would there be some benefit to selecting Hospitality, as we are within the "project's team choice" 40-60% floor...

Last reply: Tristan Roberts, Apr 10, 2016, 8:16 am

EAP2 required HAP input summary

NC-2009 EAp2: Minimum Energy Performance
posted by Eric Wright on Apr 1, 2016, 7:26 pm

For the EAP2 upload EAP2-14 LEED is asking for the modeling software "input summary." What specific input summaries are required for Carrier HAP? I am modeling a building over 100,000 sq ft. The...

Last reply: Marcus Sheffer, Apr 9, 2016, 6:20 pm

existing building modeling

CS-2009 EAp2: Minimum Energy Performance
posted by Alfonzo Collins on Apr 8, 2016, 3:32 pm

I am modeling an existing building right now. The opaque envelope will be maintained (walls and roof) but the entire inside, all HVAC systems, and windows will be replaced. For the model, I...

Last reply: Marcus Sheffer, Apr 9, 2016, 6:18 pm

n/a

NC-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Donna Juselis on Apr 8, 2016, 5:59 pm

deleted

Complex Occupancy Upload PIf3-1

NC-2009 PIf3: Occupant and Usage Data
posted by Jeannie Rueter on Apr 7, 2016, 5:39 pm

The requirement for this upload is to provide project...

Last reply: Deborah Lucking, Apr 8, 2016, 11:24 am

Commercial Kitchen

CS-2009 IEQc8.2: Daylight and views - views
posted by José Solis on Apr 8, 2016, 10:37 am

I have a mixed use office building with the potential for restaurant tenants on the ground floor. There is sufficient exterior glazing for tenants to easily meet this credit if they use open...

Last reply: TODD REED, Apr 8, 2016, 11:06 am

Street trees in a winter resort

Pilot-Credits PC14: Walkable Streets
posted by John Zehren on Apr 7, 2016, 6:48 pm

Our project is bounded by a stream on one side, a road on another and 2 sides are on an active pedestrian mall (non motorized) with retail and restaurants meeting the height to width ratio. This...

Question about terrace without roof

CI-2009 IEQc8.1: Daylight and views - daylight
posted by Haoyang Li on Apr 6, 2016, 11:32 pm

Hi all,
I am working on a commercial interior university restaurant project. There is a non-roof terrace at 3rd floor. This terrace is located at the west side of the main building which...

Last reply: Haoyang Li, Apr 7, 2016, 1:29 pm

What is a wetland or naturally designed pond per credit language

CS-2009 SSc5.2: Site development - maximize open space
posted by Landry Watson on Apr 5, 2016, 4:45 pm

Credit language clearly indicates that wetlands and naturally designed ponds can count as long as their sides are vegetated and their gradient no more than 1:4. Are stormwater detention/...

Last reply: Saurabh Shrestha, Apr 6, 2016, 10:39 pm