Small study rooms- 2-3 rooms per thermostat

NC-2009 IEQc6.2:Controllability of Systems—Thermal Comfort
posted by  Katie Schulze  on 

I am working on a library that has tons of spaces that can meet the needs of individuals or multiple occupants. In the case of the small study rooms, I am qualifying them as multi-occupant rooms.

2
Tue May 7, 2013, 10:31 pm

Energy modeling Gross Surface / Net surface.

CS-2009 EAp2:Minimum Energy Performance
posted by  Alessio Zampaglione  on 

Section 1.2 Space summary in prerequisite EAp2 asks for GrossSquareFootage (GSF) of regularly and unconditioned zones.

10
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue May 7, 2013, 1:50 pm

Filling out EAp2 form

CS-2009 EAp2:Minimum Energy Performance
posted by  Ron Dean  on 

Hi everyone, I have the three following questions: 1. In the EAp2 form, I have to write the HDD and CDD for Lima, Peru.

3
Default Avatar
Sumac Inc.
LEEDuser Basic Member
20 thumbs up
Tue May 7, 2013, 12:19 pm

Pilot Credit #44 Ergonomics Strategy - LEED User registration

Pilot-Credits EQpc44:Ergonomics approach for computer users
posted by  Cindy Davis  on 

I received a comment back from our LEED preliminary design review that the 'reviewer' is unclear if the project team representative (me) has registered with LEEDuser, since a completed survey has n

5
Associate Vice President
CallisonRTKL
LEEDuser Basic Member
16 thumbs up
Tue May 7, 2013, 2:05 am

Sub-metering in Option D

NC-2009 EAc5:Measurement and Verification
posted by  Alicia Villanueva  on 

Marcus Sheffer posted some months ago in this credit: "You will need to calibrate the model by energy end use on a monthly (and annual) basis. [...] Yes you would need to separate out the electric

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon May 6, 2013, 10:57 pm

MPR#6 - Option 1: Sharing data via Energy Star Portfolio Manager

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Ron Dean  on 

One of the projects I'm working on in Peru, is persuing the option 1 of MPR#6 (through Energy Star Portfolio Manager:ESPM) so we can get one EP point in EAc5.1. So, my questions are: 1.

3
Default Avatar
Sumac Inc.
LEEDuser Basic Member
20 thumbs up
Mon May 6, 2013, 6:36 pm

No new parking, can we still achieve Option 1?

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Eamon Geary  on 

The project I am working on is a new facility on a pre-existing campus. There are is no new parking added and all new employees are expected to find parking spots on their own.

7
Mon May 6, 2013, 5:44 pm

Biomass from energetic crops

CS-2009 EAc2:On-site Renewable Energy
posted by  BH .  on 

Hi, does LEED recognize the biomass from energetic crops such like: -short rotation coppice (Poplar and willow include) -Grasses and non-woody energy crops (Miscanthus and Hemps included) Tha

3
Default Avatar
LEEDuser Basic Member
52 thumbs up
Mon May 6, 2013, 3:19 pm
15
Default Avatar
Associate
Wallace Roberts & Todd, LLC
LEEDuser Basic Member
4 thumbs up
Mon May 6, 2013, 2:44 pm

Consistency in regularly occupied and unconditioned areas

NC-2009 PIf3:Occupant and Usage Data
posted by  Alicia Villanueva  on 

My project team is aware that the total gross area must be consistent through PIf3 and EAp2 forms. We wonder whether or not it is also required to have consistency in "regularly occupied" and "unc

3
Mon May 6, 2013, 2:33 pm