Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Reciprocity b/w ESv3 and LEED MF midrise

Mid-Rise-v4 EAp1:Minimum energy performance
posted by  Smita Thomas  on 

A client needs an energy model for a multifamily midrise that is applying for LEED v4 and also applying for Energy Star.

3
Default Avatar
Principal
Energy Shrink, LLC
LEEDuser Basic Member
1 thumbs up
Fri Jul 21, 2017, 4:39 pm

small community adjustment

NC-v4 LTc5:Access to quality transit
posted by  nancy picard  on 

For LEED 2009, there was CIR 431 from the CaGBC that adjusted frequency for communities under 50,000 people. Is there a similar adjustment acceptable for LEED v4?

2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Fri Jul 21, 2017, 1:18 pm

Is Education still acceptable?

NC-v4 INc1:Innovation
posted by  Deborah Lucking  on 

Does anyone have any insight on whether Education is still an acceptable way for a project to achieve an Innovation credit point under LEEDv4? Thanks!

7
Director of Sustainability
Fentress Architects
LEEDuser Expert
224 thumbs up
Thu Jul 20, 2017, 10:01 pm

Water Bottle Filling Stations

NC-2009 WEc3:Water Use Reduction
posted by  Norma Lehman  on 

do these count in our standard water calculations? if not, can we include them as process water to earn exemplary?

5
Sustainable Design Consulting
LEEDuser Basic Member
20 thumbs up
Thu Jul 20, 2017, 7:21 pm

Construction and Demolition Waste Management Plan

NC-v4 MRc5:Construction and demolition waste management
posted by  milo valenti  on 

we are looking for an excel template to do the following! tracking truck picks up C+D takes it to recycling facility!That ticket is expanded into a excel sheet to track what was recycled from that

4
coo
Cleveland Carting, llc
LEEDuser Basic Member
0 thumbs up
Thu Jul 20, 2017, 4:42 pm

occupancy sensor in big offices

NC-v4 EAp2:Minimum energy performance
posted by  Francesco Passerini  on 

I read in paragraph 9.4.1.2 b. that "an occupant sensor or a timer switch shall be installed (...) in: (...) 6. office spaces up to 76.2m2". Does it mean that for bigger offices (i.e.

5
Thu Jul 20, 2017, 4:08 pm

Option 3 fueling capacity determined by time limit?

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Erica Downs  on 

Our project is at a large university, and a 2-plug Level 2 station has been installed.

9
Default Avatar
Sustainability Analyst
SAS Institute Inc.
LEEDuser Premium Member
5 thumbs up
Thu Jul 20, 2017, 3:51 pm

End Uses

NC-2009 EAc5:Measurement and Verification
posted by  Matthew VanSweden  on 

I realize that EAc Advanced Energy Metering is not listed in the v4 credits that you are allowed to use on v2009 projects but has anyone had any success utilizing the v4 metering language of "insta

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 20, 2017, 2:43 pm

LEED CI 2009 Innovation option: Monitoring Based Commissioning

CI-2009 IDc1:Innovation in Design
posted by  Margaret Montgomery  on 

This option in the innovation catalog is noted as adapted from LEED v4 EAc Enhanced Cx, and I'm not clear if it would be counted as an additional above-2009-enhanced-cx strategy, or if it's somehow

2
Default Avatar
LEEDuser Expert
472 thumbs up
Thu Jul 20, 2017, 2:37 pm

AHU LEED Certificate

NC-2009 EAc5:Measurement and Verification
posted by  Tota Yun  on 

We got this quote from manufacturer regarding AHU compliance ((While some sections of this standard do not apply to our product, we do comply with the sections that apply. According to the standa

3
Default Avatar
LEEDuser Basic Member
0 thumbs up
Thu Jul 20, 2017, 2:17 pm