Habitat for endangered/threatened species

NC-2009 SSc1:Site Selection
posted by  Ashley Hu  on 

Hello there,

I have two project sites in question.

1) An very urban site that was previously a parking lot

0

Low flow aerators to account for reductions instead of metering

NC-v4 WEp2:Indoor water use reduction
posted by  S. Sachs  on 

Has anyone worked with low flow aerators instead of metering since metering is no longer allowed for v4?

4
Fri Nov 3, 2017, 6:04 pm

What % difference to reference is acceptable?

NC-v4 SSc2:Site development - protect or restore habitat
posted by  Leanne Conrad  on 

We are pursuing the chemical testing path for imported soils. My question is what is the acceptable range or percent difference between the reference and imported soils?

1
Fri Nov 17, 2017, 1:04 am

Bicycle network distance to entrance

NC-v4 LTc5:Access to quality transit
posted by  Ricardo Sá  on 

I'm working on a project that consists of a new office building that will be constructed on top of an existing shopping center.

2
Default Avatar
VP of Innovation
Sustainable Investment Group
LEEDuser Basic Member
110 thumbs up
Fri Nov 3, 2017, 3:56 pm

Previously Developed and Greenfield Site

CS-2009 SSc2:Development Density and Community Connectivity
posted by  Michelle Rosenberger  on 

Our project is on a large master planned site. Parts of the site had single family homes and fuel tanks years ago.

3
Fri Nov 3, 2017, 2:28 pm

Made to measure Furniture

NC-v4 EQc2:Low emitting materials
posted by  Charline SEYTIER  on 

Our client is willing to install made to measure furniture that will be composed of elements from 2 pieces of furniture that meet the credit requirements.

1
Fri Nov 3, 2017, 11:03 am

Cooling Towers

CI-v4 EAp3:Fundamental refrigerant management
posted by  Laura Charlier  on 

If cooling tower is being replaced as part of project, does that need to be included in calcs?

0

What's the size requirement for a Data Center Project with LEED v4 BC+D and O+M?

EBOM-v4 MPR3:Must comply with project size requirements
posted by  Xiaoyu Cao  on 

Hi,

I see the minimum size requirements for BD+C and O+M is ,

"LEED BD+C and LEED O+M Rating Systems

1
Thu Nov 2, 2017, 4:12 pm

Walkable Project Site

NC-v4 INc1:Innovation
posted by  Quentin Jackson  on 

Hi all,

I'm working on a stadium project in Australia and we're looking at the walkable project site innovation credit.

1