How to achieve controllability for an arena

NC-v4 EQc5:Thermal comfort
posted by  Helene Lefkowitz  on 

Hello - The project I am working on will have an arena and auction hall in the building. It is my understanding these spaces are considered a shared multioccupant space per LEED.

1
Fri Dec 20, 2019, 5:57 pm

Portion of gound level paving under building

NC-v4 SSc5:Heat island reduction
posted by  Tilly Ford  on 

Hi,

I have a building for which the ground level steps back and therefore the paving is shading by the building itself. I can't quite tell how to account for this, is it either:

3
Principal
The Beck Group
LEEDuser Basic Member
98 thumbs up
Thu Feb 14, 2019, 5:18 pm

Discounted Parking Rate - How to implement?

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Michelle Bombeck  on 

I have a large mixed use retail/office project that is interested in using the discounted parking rate option to comply with this credit but is finding logistical issues.

4
Senior Principal | Director of Sustainability Integration
SmithGroup
LEEDuser Expert
43 thumbs up
Wed Feb 13, 2019, 4:27 am

ID+C or BD+C for tenant finish project?

LEED Rating System Selection
posted by  Josie Plaut  on 

We're getting started on a 14,000 SF tenant finish project within a 21,000 SF building.

1
Tue Feb 12, 2019, 1:26 pm

Advanced Energy Metering in Multi-Family Housing

NC-v4 EAc3:Advanced energy metering
posted by  Allison Wilson  on 

We're working on a dorm project with apartment style units such that it's essentially multi-family housing.

1
Fri Feb 8, 2019, 8:43 pm
1
Fri Feb 22, 2019, 7:13 pm

Modeling Refrigerant Economizer for Data Center - proposed model

NC-2009 EAp2:Minimum Energy Performance
posted by  Maria Spastri  on 

Hi, We have an office building and it's data center room has a DX cooling with refrigerant economizer.

3
Tue Feb 5, 2019, 8:56 pm

role of pilot credits

Pilot-Credits IPpc88:LEED O+M Starter Kit
posted by  Martha Norbeck  on 

We submitted a Green Cleaning policy as a BD+C LEED v4 innovation credit. The reviewers said our only option now was to submit via this pilot credit. This seems to be a huge jump in scope.

1
Mon Feb 4, 2019, 7:37 pm