Forum quick links
LEED CS 2009 - WEp1 & WEc3
CS-2009 WEp1:Water Use Reductionposted by Ruel Galve on
We are building a mixed use project, Office, Hotel and Residential to qualify for LEED CS 2009 Gold. Only the office core will have toilets that will be built during C & S construction.
Job Specific Environment Analysis
NC-2009 SSp1:Construction Activity Pollution Preventionposted by Yodi Danusastro on
Does anyone has the template of JSEA? I've been ask to create ESC with inclusion of JSEA template. Where an I find this template?
Mixed-use Building
CS-2009 SSc9:Tenant Design and Construction Guidelinesposted by Wan Ji Loo on
Hi, my project is a mix use building with two buildings connected via a commercial area below, a residential and hotel in one block and a office tower in the other.
Acoustic ceiling & gypsum board
CS-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Productsposted by Anna Okviana on
Is it enough to comply the credit by submit document from manufacture that state " Formaldehyde is NOT used in the manufacturing of these product" ?
Parking Garage Demand Controlled Ventilation
CS-2009 EAp2:Minimum Energy Performanceposted by Scott McMillan on
Hi there, When a proposed building model includes parking garage DCV based on CO - How should the control of the baseline model garage fan volume be controlled?.
LEED CS 2009 EAc1
CS-2009 EAc1:Optimize Energy Performanceposted by Ruel Galve on
We are currently doing a LEED 2009 CS - GOLD project in Jakarta. The question is: Do we need to select our equipment (pumps and fans) based on the recommended baseline building design power from A
Categorizing a LEED project
posted by Adi Negara, LEED AP BD+C on
Hello all, I have a difficulty in determining the appropriate LEED rating system for a project, and I hope that you all can tell me what rating system is best suited to the project: The project ow
Baseline HVAC Model System-8 VAV PFP Boxes with Outdoor Air Unit
NC-2009 EAp2:Minimum Energy Performanceposted by Ivan Priatman on
Dear LEED, We are designing a medical office with VRF system, to fulfill iaq requirements we add independent outdoor air unit comprises of supply and exhaust fans on each zone.
Synthetic Enamel's VOC
NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Yodi Danusastro on
Which one from the table that suits for Synthetic Gloss Enamel paint, that use for painting metals?