Can New Construction project use requirement of Warehouse and Distribution center to count point?

NC-v4 LTc4:Surrounding density and diverse uses
posted by  Michael   on 

Hi LEED expert, my project is a manufacturing plant with a warehouse. The warehouse accounts for 46% of the total GFA. The project will be registered under New Construction.

4
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Tue Apr 30, 2024, 10:23 am

Energy Modeling using “HAP”

NC-2009 EAp2:Minimum Energy Performance
posted by  Muzamil Rafique  on 

I am doing the energy model for a project.

9
HVAC DESIGN ENGINEER
IES Consulting
LEEDuser Basic Member
17 thumbs up
Tue Mar 26, 2024, 11:46 pm

Modeling only conditioned area

NC-v4 EAp2:Minimum energy performance
posted by  Omar Elrawy  on 

I'm certifying a huge factory with an attached office building. Is it possible to model only the office area?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Mar 25, 2024, 5:38 am

What is the Exact Definition of A Trip?

NC-v4 LTc5:Access to quality transit
posted by  Krithikha Muthukrishnan  on 

I am posting this question largely because the credit langauage is not very clear(maybe language nativity issues here). In the Reference Guide, "A Trip" is defined as follows-

2
Mon Mar 4, 2024, 2:29 pm

Projects with several distinct structures

Hospitality-NC-v4 MPR3:Must comply with project size requirements
posted by  Manzil Shrestha  on 

"Any single structure that is larger than 25,000 square feet (2 320 square meters) must be registered as a separate

0

FEES FOR BASEMENT AREA

LEED v4.1 Discussion Forum
posted by  Subrota Roy  on 

 Is it necessary to calculate the basement area when we calculate the gross floor area?For feea. If this area is not only used as parking but also used as some function as storage.

0

Multilevel lighting control

NC-v4.1 EQc6:Interior Lighting
posted by  Michael   on 

I have 10 lighting fixtures in an office space, and the architect is providing 3 on-off switches:

- switch 1, on-off 5 lightings (50% of lighting numbers)

6