Forum quick links
Baseline System 8
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, Just a small clarification about the heating plant of System 8. It is written that heating is Electric resistance.
Compressor replacement + R422D refrigerant
EBOM-2009 EAc5:Enhanced Refrigerant Managementposted by Norbert Szircsak on
Dear All, I have two issues where I don't really know what would be the proper solution. 1. After about 10 years one of the compressors in a chiller went wrong and has been replaced.
IEQp1 VRP Calculator
CI-2009 IEQp1:Minimum IAQ Performanceposted by Vassil Vassilev on
Greetings, Regarding IEQp1 and VRP Compliance Calculator there is a question on how to enter an AHU having the following characteristics: The AHU is a constant volume device; supplying to several
Invoice Requirements
CS-2009 MRc6:Certified Woodposted by Charles Nepps on
Per the the FAQ's above: "GBCI had required invoices for all wood products, but has switched to requiring only invoices for FSC certified products, per the April 2008 FSC memo, which states that al
No local zoning requirements
NC-2009 SSc4.4:Alternative Transportation—Parking Capacityposted by Agnieszka Rylska on
Is there an Alternative Complance Path for projects outside the US with no minimum local zoning requirements?
What is to be considered LID + measures outside LEED Site
NC-v4 SSc4:Rainwater managementposted by Petr Vogel on
Dear all, we have a project site situated in the rural mountains where infiltration is not even possible due to geological conditions.
Scope of the credit
posted by Frantisek Macholda on
Hello, I am not sure if this credit covers the equipment purchased for building management purposes only (i.e.
Baseline modeling for manufacturing facility
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Hi Markus and colleagues, There are few issues which I'd like to share, with a request for some advice related to the Baseline project modeling. The project in question is a manufacturing facility
distance between shower rooms and changing rooms
CI-2009 SSc3.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Anastasia Makarenko on
We currently have a project LEED-CI. It's an office in which there are 4 shower rooms for 730 FTE. There are 4 floors so we have one shower room per one floor.
Interior Lighting power
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Hi Markus and colleagues, If in the Proposed building the total interior lighting power (space by space method) is bigger than those of the Baseline, is this acceptable.