Temporary vs. Permanent Power

NC-2009 MPR6:Must commit to sharing whole-building energy and water usage data
posted by  Donald Green  on 

I posted this under MPR2 but thought I might get a response under this MPR as well... We have a project that may not have its permanent power for as long as a year after occupancy.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Apr 29, 2014, 8:00 pm

IEQc3.2 Option 2: Air Testing

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Christopher Strunk  on 

Currently doing a LEED v.2009 project and are looking to pursue IEQc3.2, Option 2. We got a question from the air quality tester asking about the specific requirements for testing.

2
Default Avatar
LEED AP (O+M)
4 Elements Group
LEEDuser Basic Member
34 thumbs up
Tue Apr 29, 2014, 7:11 pm

2009 BD+C/ID+C Calculation problem for Heat Island Effect - Roof

CI-2009 SSc1:Site Selection
posted by  Laurie Thorwart  on 

Hey all, Please bear with me, as this question is complicated and takes into account a couple different documents/rating systems.

3
Tue Apr 29, 2014, 5:42 pm

Liquid Ice Melt

EBOM-2009 SSc2:Building Exterior and Hardscape Management Plan
posted by  cathy keagle  on 

Can anyone provide guidance on the types of Liquid Ice Melt that would satisfy the requirements of this credit?

3
Tue Apr 29, 2014, 5:32 pm

Raw Material Extraction/Harvest Locations

NC-2009 MRc5:Regional Materials
posted by  Dianne Carey  on 

We manufacture coating and adhesive products. Determining the point of extraction/harvest of our raw materials is becoming more and more difficult to "trace".

13
Director of Technical Services
W. R. MEADOWS, Inc.
LEEDuser Basic Member
0 thumbs up
Tue Apr 29, 2014, 3:39 pm

Rainwater harvesting

NC-v4 SSc4:Rainwater management
posted by  Erin Holdenried  on 

Will rainwater harvesting prevent compliance with this credit?

3
Default Avatar
Sustainability Architect
LEEDuser Basic Member
88 thumbs up
Tue Apr 29, 2014, 2:56 pm

Stone Counter adhesive

CI-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Meredith Park  on 

We are running into an issue with the stone counter top adhesive. The typical product that our sub uses is "Superior Gold Knife Grade" and it does not meet the limits.

3
Tue Apr 29, 2014, 12:31 pm

Future Use Classroom

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Omar Elrawy  on 

Dear all, I'am working on an office building with complete furniture design except for one space (room); a classroom which is intended for future use so the owner isn't willing to plac

3
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Mon Apr 28, 2014, 3:00 pm

On-going Commissioning

NC-2009 IDc1:Innovation in Design
posted by  David Edenburn  on 

Has anyone been able to use EBOM EAc2.3 (On-going Commissioning) as an ID point for a LEED-CI project?

2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Sun Apr 27, 2014, 2:04 pm

E-Cloth

EBOM-2009 IEQc3.3:Green Cleaning—Purchase of Sustainable Cleaning Products and Materials
posted by  Erin Nuckols  on 

Has anyone heard of a product called E-Cloth? If so, do you know if it meets any of the criteria for this credit?

7
Sustainable Building Consultant
Green Bridge Consulting
LEEDuser Expert
28 thumbs up
Fri Apr 25, 2014, 8:25 pm