Forum quick links
Alternative approach to SS credits than the campus approach
NC-2009 SSc2:Development Density and Community Connectivityposted by JASON BONE on
Our new construction project is a new fitness center on the periphery of a community college campus, which is adjacent to a landscape valley (with no density).
Using different energy rates between CHP Proposed and Baseline
NC-v4 EAp2:Minimum energy performanceposted by Mark Benson on
I know that the 90.1 and the LEED Reference Guide generally tell you to use the same utility rate structures for both the Proposed and Baseline models.
Lease requirements for this credit
CS-2009 IEQc2:Increased Ventilationposted by Troy Glasner on
Hi, I am just wondering what specific lease requirement language would be needed for this credit.
LEED lease agreement for CS
CS-2009 IEQc2:Increased Ventilationposted by Alfonzo Collins on
I am working on a core & shell building. The owner will only be installing AHUs for a few core & shell spaces.
Can Building Envelope CxA be the acoustical engineer
NC-v4 EQc9:Acoustic performanceposted by Edgar Arevalo on
I know under LEED that the design engineers cannot also be the Cxa, but does that also apply for an entity/company who is the building envelope CxA but can also be the acoustical engineers?
ASHRAE Guideline 0 2005 or newer?
NC-v4 EAc1:Enhanced commissioningposted by Walter Broner on
For EA prerequisite, the standard for commissioning that is referenced by USGBC (the 2005 edition) is now outdated. Should that standard be used or tne new updated one?
Disconnect within Pilot Credit Database
Pilot-Credits MRpc52:Material multi-attribute assessmentposted by Kristina Bach on
The currently requirements (Option 1 - EPD) do not appear to be in-line with the credit-specific requirements/additional questions.
FGI guidelines
Healthcare-v2009 MRp1:Storage and collection of recyclablesposted by Michael Boyle on
Hello, I am working on a hospital building and would want to know the sizing and location requirements for recycling as per the FGI guidelines? Appreciate all the help i can get! Thanks,
Commercial Kitchen and Gym Equipment
CI-v4 WEc1:Indoor water use reductionposted by Alexander Spilger on
Our project is a large office TI with all of the typical water fixtures such as wash closets, urinals, showerheads, sinks, etc.
Overlaying two daylight simulation results
CS-2009 IEQc8.1:Daylight and Views—Daylightposted by GBD Architects on
Hi all, In relation to my last comment (below), do folks have good/simple strategies for overlaying their daylight results from Insight (AutoDesk product) to get your compliant SF? Thanks, Hannah