Documenting On Site Water Reuse
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Saud Abdul Rasheed on
Hello All, In our Project we are installing a Water Treatment Plant where we are collecting grey water from sinks as well as capturing rain water and treating them and using them in the flushing o
2009 and V4
posted by H KACI on
Hello everyone I have decided to take the exam just before the system changes to V4. I ha a couple of questions: 1- Comparing the specifications of 2009 and V4 , it seems the latter is much more si
VOC Classification for Concrete items
NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Mariah Grife on
I have a number of items used for concrete - Form Release Compounds and Concrete Surface Retarders, as well as Cable pulling Lubricant used by the electricians on my project.
CS but last minute changes indicate NC..... what to do?
posted by Melissa Merryweather on
We have been working for over 2 years on the design submittal of a very large LEED CS office tower, but the lease area has always been somewhat unclear and now, only a few weeks away from completin
Verbiage for Policies and Plans
EBOM-2009 MRp1:Sustainable Purchasing Policyposted by Sara Zoumbaris on
Hello, We are working with a city government to certify several buildings under LEED EBOM.
How do we address non-certifiable Parking Garage ?
CS-2009 MRc4:Recycled Contentposted by natalie tan on
HI, I previously posted a similar message in the MPR forum but there was no reply and am reposting it here as it pertains to MRc4/c5/c6.
Strategies to avoid high illuminance level
NC-v4 EQc7:Daylightposted by SSN Energy Model on
Hello everyone, Greetings for the day We are doing daylighting simulation for the project which will be registered under LEED Version 4. As per the requirements of LEED v4 EQ Cr7, the project shoul
designation of CXA as required by LEED
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Benjie Herrera on
I just want to ask for a comment if the Owner is the only one who can designate a commissioning authority(CXA) for the project...
Which Rated Life per bulb is to be used in calculations?
EBOM-2009 MRc4:Sustainable Purchasing—Reduced Mercury in Lampsposted by Vivek Singla on
I found the following life values in the Bulb specifications. Which rated life is to be used in the LEEDOnline form for this credit?
Baseline HVAC System Types - Number of floors
NC-2009 EAp2:Minimum Energy Performanceposted by CT G on
Dear all, In the selection of the HVAC system for baseline according to Table G3.1.1A should the unconditioned underground parking pavements be considered in the number of floors of the building?