posted by Sheena Moses on Aug 23, 2017, 2:54 am

We are currently working on an...

Last reply: Ben Stanley, Aug 29, 2017, 12:01 pm

Facilities and alterations. Outside the building

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by Mercè Llorca on Aug 1, 2016, 8:04 am

There are outside works planned to be done. I understand that LEED reference guide definition is focused only in indoor alterations, mainly when talking about air quality because I don't see how...

Last reply: Kimberly Schlaepfer, Aug 12, 2016, 6:00 pm

Replace All Filtration Media

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by Ran Zhang on Jun 14, 2016, 2:36 am

Hi I am working on a project located in Tokyo Japan. We are aiming to pursue IEQ c1.5 and thinking about the requirements regarding the filtration media replacement right now. As replacing all...

Last reply: Trista Brown, Jun 14, 2016, 3:02 pm

Performance period and construction

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by Kasandra Martin on Apr 23, 2016, 11:50 am

Our project is in the process of building an addition. The performance period is not yet started. Will this credit not work because the construction will be completed and become occupied all...

Last reply: Kasandra Martin, Apr 25, 2016, 4:41 pm

Building Flush out for naturally ventilated building

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by PRATIK KUMAR on Mar 12, 2016, 10:31 am

Under EBOM IEQ-Cr-...

Last reply: Trista Brown, Mar 15, 2016, 10:11 pm

construction completion date is outside of performance period

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by Jessica Hawley on Apr 14, 2015, 2:15 pm

We are currently in our performance period for a project where a tenant fit out of a vacant floor is currently in the planning stages & construction may or may not start during our...

Last reply: Trista Brown, Jan 4, 2016, 4:37 pm

management plan update after preliminary review

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by Noriko Nagazumi on Mar 20, 2015, 4:09 am

We received a comment to revise our management plan on the preliminary review.

Should we update the date of the plan? The date would come after the performance period...

Last reply: Trista Brown, Jan 4, 2016, 4:30 pm

Minimum square area for facility alteration/ addition

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by Magda Aghababyan on Jun 4, 2013, 5:33 am

We are doing a project that has 3 buildings out of which one is a two storied building. The proposed facility alteration/ addition project is on the upper floor of this two storied building where...

Last reply: Tristan Roberts, Nov 4, 2013, 10:08 pm

Building flush out for several small alterations

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by Julie Pollack on Mar 14, 2013, 3:35 pm

There will be several small building alterations completed to our project building during the performance period (vestibule and lobby upgrades, demo and tenant finish build out for entire floor,...

Last reply: Julie Pollack, Mar 29, 2013, 1:12 pm

Building flush-out of entrance vestibule

EBOM-2009 IEQc1.5: Indoor air quality best management practices - indoor air quality management for facility additions and alterations
posted by Julie Pollack on Dec 19, 2012, 2:23 pm

During the performance period for LEED...

Last reply: Julie Pollack, Jan 14, 2013, 3:22 pm