Our project is in the process of building an addition. The performance period is not yet started. Will this credit not work because the construction will be completed and become occupied all before the perfomance periods would start?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Trista Brown
Project DirectorWSP USA
456 thumbs up
April 23, 2016 - 9:45 pm
Hi Kasandra, the performance period for any credit or prerequisite can be up to 2 years long. Just remember that all performance periods in the application must end in the same 30-day window. In this case perhaps you can extend the performance period back for this credit to capture this addition.
Kasandra Martin
Designer3 thumbs up
April 25, 2016 - 4:41 pm
OK So I can extend the PP for just this credit back so it could be included.